Question
|
|
Date:
|
10/21/2026 10:49:29 AM
|
|
Bridge plan sheet 1 general nots state the color for painting of bridge beams. There is no pay item for painting the steel. Will a pay item be added?
|
|
Answer
|
Date:
|
10/21/2026 1:47:21 PM
|
|
No. Per Section 411.11 of the Specifications, coating of new metal on structures will not be measured for separate payment but shall be included in the price for structural steel.
|
|
|
|
|
|
Question
|
|
Date:
|
10/9/2026 11:36:54 AM
|
|
The posted notice references A99 rather than A98. Please confirm that the notice pertains to VDOT Project A99 and not this project.
|
|
Answer
|
Date:
|
10/9/2026 1:36:51 PM
|
|
The A98 addendum has been posted. Thank you.
|
|
|
|
|
|
Question
|
|
Date:
|
10/9/2026 11:36:52 AM
|
|
The posted notice references A99 rather than A98. Please confirm that the notice pertains to VDOT Project A99 and not this project.
|
|
Answer
|
Date:
|
10/9/2026 1:37:04 PM
|
|
The A98 addendum has been posted. Thank you.
|
|
|
|
|
|
Question
|
|
Date:
|
10/7/2026 2:56:58 PM
|
|
Sheet 66G(10) provides a table of temporary pavement elevations to build up asphalt on the existing shoulder and construct the MB-8A barrier in Phase 2. Note #4 states the MB-8A barrier will be removed and replaced to final barrier elevations in Phase 4 from 112+50 to 115+50. However, the table provides temporary elevations for most of the barrier to be placed in Phase 2. Please confirm all MB-8A barrier that is installed in Phase 2 and required to be replaced in Phase 4 will be compensated under appropriate pay items (Median Barrier MB-8A and Remove Existing Concrete Barrier), with exception of the ten (10) foot transitions to tie into existing barrier.
|
|
Answer
|
Date:
|
10/8/2026 10:38:48 AM
|
|
All MB-8A barrier that is installed in Phase 2 and required to be replaced in Phase 4 will be compensated under appropriate pay items (Median Barrier MB-8A and Remove Existing Concrete Barrier), with exception of the ten (10) foot transitions to tie into existing barrier.
|
|
|
|
|
|
Question
|
|
Date:
|
10/6/2026 5:32:36 PM
|
|
Please confirm it is the department's intent to install MB-8A from 112+50 to 115+50 in phase 2, then remove and replace in phase 4 per note 4 on page 66 G(10).
|
|
Answer
|
Date:
|
10/7/2026 3:12:03 PM
|
|
It is the department's intent to install MB-8A from 112+50 to 115+50 in phase 2, then remove and replace in phase 4 per note 4 on page 66 G(10) to accommodate the different pavement elevations in each phase.
|
|
|
|
|
|
Question
|
|
Date:
|
10/6/2026 5:31:48 PM
|
|
Please indicate if VDOT will enforce note 19 on plan sheet 66 E(1) with regards to trucks entering and exiting the jobsite.
|
|
Answer
|
Date:
|
10/7/2026 3:11:29 PM
|
|
The contractor may utilize the construction entrances during daytime hours without closing a lane if they can demonstrate that they can enter and exit the work zone safely without disrupting interstate traffic.
|
|
|
|
|
|
Question
|
|
Date:
|
10/6/2026 5:31:22 PM
|
|
The first general note on bridge sheet 2 states "pier demolition shall not be performed until after all existing beams have been removed. Partial demolition prior to Phase 4 construction will not be allowed." Can the abutments be partially removed in phase 3?
|
|
Answer
|
Date:
|
10/7/2026 3:11:05 PM
|
|
The abutments can be partially removed in Phase 3.
|
|
|
|
|
|
Question
|
|
Date:
|
10/6/2026 5:30:52 PM
|
|
Sheet 66 T(02) indicates there is 200 LF of MB-8A Type II on sheet 66L, 100 LF on sheet 66M, and 400 LF on sheet 66N. Sheets 66 K to 66-O have zero indication of MD-8A Type II anywhere on the sheets. Additionally, the quantities on 66 T902) does not match the actual taken off quantities on the individual sheets 66 K - 66-O. Please advise.
|
|
Answer
|
Date:
|
10/7/2026 3:10:17 PM
|
|
Quantities on sheet 66T(2) include the barrier that is to be constructed in Phase 2 and replaced in Phase 4 per note 4 on sheet 66G(10). There is no callout for MB-8A Type II on sheets 66 K - 66-O. Refer to sheet 66G(10) for locations where Type II is required.
|
|
|
|
|
|
Question
|
|
Date:
|
10/6/2026 8:59:17 AM
|
|
Will the Department allow for the storm pipe run 5-4 to 5-1 be jacked & bored due to maintaining positive drainage with the phasing of the project? If this storm pipe can be jacked and bored, will the department allow for the casing pipe to serve as the carrier pipe?
|
|
Answer
|
Date:
|
10/7/2026 11:23:06 AM
|
|
If requesting a modification to the plans, refer to Section 104.02(C) of the Specifications.
|
|
|
|
|
|
Question
|
|
Date:
|
10/12/2026 3:28:11 PM
|
|
To follow up on the drainage question from 10/06, it was not intended to propose this as a potential VECP. The intent was to point out that due to the phasing of the work, the upstream end of pipe run 5-4 to 5-1 will be installed prior to the downstream end. This means that water will collect with nowhere for it to go. Therefore, to allow for the proper construction of the pipe run, will the Department change this run to a jack & bore and will the casing pipe be allowed to serve as the carrier pipe?
|
|
Answer
|
Date:
|
10/13/2026 3:37:00 PM
|
|
The intent of the design is to install the downstream end in Phase 3 and connect to the existing pipe. The remainder of the pipe can be installed in Phase 4. Plans will not be adjusted to require jack and bore.
|
|
|
|
|
|
Question
|
|
Date:
|
10/6/2026 8:57:39 AM
|
|
Proposal Page 97: The SP for Mass Concrete is included in the Proposal, however, there appears to be no concrete on the project which classifies as Mass Concrete. Please clarify where there is Mass Concrete on this project or if this SP should be removed from the Proposal.
|
|
Answer
|
Date:
|
10/7/2026 12:07:52 PM
|
|
The SP for Mass Concrete does not apply to this project.
|
|
|
|
|
|
Question
|
|
Date:
|
9/28/2026 4:06:28 PM
|
|
Plan Sheet 66 V: There is no time-of-year restriction for protected bat species in the Environmental Commitment Summary Sheet. However, in the Nationwide Permit 23, a tree cutting restriction of April 1 through November 14 is noted. Please clarify if the tree clearing restriction is required on this project.
|
|
Answer
1 previous answer(s)
|
Date:
|
9/30/2026 2:32:49 PM
|
|
There is a tree cutting Time of Year Restriction from April 1st through November 14th. A special provision will be incorporated in an upcoming addendum.
|
|
|
|
|