Advertisements
Division Home
Bid Results
Bid Tabs
Ad Report
VDOT Forms
Login Or Create Account
Project Info
Order Number
UPC
State Project Number
Last Date to Post Questions
A94
124095
0008-060-891, M501
8/21/2026
Search Questions
Search
Question Type
All
Plan
Proposal
Bid Sheet
Permits
Specifications
Other
Question Type must be selected.
The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered.
Export Q&A
Question List
Subject:
Eradication of Pavement Markings
Type:
Plan
Question
Date:
8/20/2026 8:59:34 AM
Between STA 10+75 to approximate STA 102+85 the double yellow line splits (provides median). Can these lines be eradicated such that the two temporary 10' lanes ae continuously side by side throughout the project? The concrete quantities for curb and gutter are insufficient for the concrete plant to open at night and incidental concrete pours needs to occur during regular business hours.
Answer
Date:
8/21/2026 3:35:13 PM
No, the separation is required for traffic safety related to on-coming conflicting vehicles in the northbound left turn lane.
Subject:
Traffic Maintenace Plan
Type:
Plan
Question
Date:
8/20/2026 8:27:54 AM
With the west side of RTE 8 widening complete and two 10' lanes open to traffic , can storm drainage and curbing along the east side of RTE 8 be installed during daylight hours?
Answer
Date:
8/21/2026 3:34:52 PM
Work in compliance with the Limitation of Operations as indicated on Plan Sheet 1J(1) would not be prohibited.
Subject:
Traffic Maintenance Plan
Type:
Plan
Question
Date:
8/20/2026 8:25:03 AM
Plan sheet 1J(2) shows completion of widening (to include curb and gutter and paving) along west side of RTE 8 from STA 104+25 to STA 110+ 50. Plan sheet 1J(1) indicates storm drainage along west side of RTE 8 ( 4-4 to 4-14 to 4-15 to 4-3) is not to be installed until Stage 6. Is there a reason the west side of RTE 8 storm drainage cannot be installed in stage 2? It must be in place in order to install curb and gutter.
Answer
Date:
8/21/2026 3:34:40 PM
Storm sewer structures 3-5 through 4-4 cannot be installed in stage 2 because the existing storm sewer system must continue to convey drainage from the south and east until later phases when the proposed systems to the south and east are constructed.
Subject:
Geotechnical
Type:
Other
Question
Date:
8/17/2026 4:01:09 PM
Please post any available soil reports
Answer
Date:
8/20/2026 9:52:06 AM
The soil report has been posted.
Displaying questions 1 - 4 (of 4)
Page:
1
First
Previous
Next
Last
Construction Advertisement Bulletin Board (CABB)
Update Profile
CABB v2.0
© 2008 Virginia Department of Transportation
9/20/2026 9:58:27 AM
2008