Advertisements
Division Home
Bid Results
Bid Tabs
Ad Report
VDOT Forms
Login Or Create Account
Project Info
Order Number
UPC
State Project Number
Last Date to Post Questions
L58
122820
0003-088-779, N501
4/17/2026
Search Questions
Search
Question Type
All
Plan
Proposal
Bid Sheet
Permits
Specifications
Other
Question Type must be selected.
The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered.
Export Q&A
Question List
Subject:
Minimum Percentages
Type:
Other
Question
Date:
4/9/2026 11:15:31 AM
Is there a minimum percentage of the project to be performed by the General Contractor?
Answer
Date:
4/10/2026 1:15:06 PM
In accordance with Section 105.06 of the Contract Specifications, the General Contractor is required to perform, with its own organization, work amounting to not less than 30 percent of the total contract value.
Displaying questions 1 - 1 (of 1)
Page:
1
First
Previous
Next
Last
Construction Advertisement Bulletin Board (CABB)
Update Profile
CABB v2.0
© 2008 Virginia Department of Transportation
10/18/2026 12:31:45 PM
2008