Question
|
|
Date:
|
1/23/2026 8:49:35 AM
|
|
Is the quantity of 13.15 tons of lime accurate for bid item 0170? If so, what is the intended use?
|
|
Answer
|
Date:
|
1/30/2026 2:50:01 PM
|
|
This will be addressed via a forthcoming addendum. (Receipt of bids has been delayed.)
|
|
|
|
|
|
Question
|
|
Date:
|
1/22/2026 12:02:03 PM
|
|
The proposal does not match plans for PCMS Hours . Please advise.
|
|
Answer
|
Date:
|
1/30/2026 2:50:18 PM
|
|
This will be addressed via a forthcoming addendum. (Receipt of bids has been delayed.)
|
|
|
|
|
|
Question
|
|
Date:
|
1/22/2026 10:23:27 AM
|
|
Will the department allow a mix-in-place method for the Cement Treated Aggregate?
|
|
Answer
|
Date:
|
1/30/2026 2:50:47 PM
|
|
This issue will be addressed via a forthcoming addendum. (Receipt of bids has been delayed.)
|
|
|
|
|
|
Question
|
|
Date:
|
1/13/2026 11:27:58 AM
|
|
Is it the intent of the Department for the entire diversion to be constructed of CTA?
|
|
Answer
|
Date:
|
1/16/2026 11:27:17 AM
|
|
No, the CTA shall be placed as a pavement surface for the diversion from STA 202+60 to 203+35. The entire diversion will not be constructed of CTA. Refer to Sheet 2A.
|
|
|
|
|
|
Question
|
|
Date:
|
1/22/2026 4:20:34 PM
|
|
We have not been able to find a supplier for Cement Treated Aggregate for this project. Please advise.
|
|
Answer
|
Date:
|
1/30/2026 2:51:01 PM
|
|
This issue will be addressed via a forthcoming addendum. (Receipt of bids has been delayed.)
|
|
|
|
|
|
Question
|
|
Date:
|
1/22/2026 4:20:33 PM
|
|
We have not been able to find a supplier for Cement Treated Aggregate for this project. Please advise.
|
|
Answer
|
Date:
|
1/30/2026 2:51:14 PM
|
|
This issue will be addressed via a forthcoming addendum. (Receipt of bids has been delayed.)
|
|
|
|
|
|
Question
|
|
Date:
|
1/20/2026 8:23:29 AM
|
|
We have not been able to find a supplier for Cement Treated Aggregate for this project. Please advise the supplier/suppliers that the Department has determined will be able to supply this product for this project.
|
|
Answer
|
Date:
|
1/30/2026 2:51:31 PM
|
|
This issue will be addressed via a forthcoming addendum. (Receipt of bids has been delayed.)
|
|
|
|
|
|
Question
|
|
Date:
|
1/22/2026 4:20:34 PM
|
|
We have not been able to find a supplier for Cement Treated Aggregate for this project. Please advise.
|
|
Answer
|
Date:
|
1/30/2026 2:51:01 PM
|
|
This issue will be addressed via a forthcoming addendum. (Receipt of bids has been delayed.)
|
|
|
|
|
|
Question
|
|
Date:
|
1/22/2026 4:20:33 PM
|
|
We have not been able to find a supplier for Cement Treated Aggregate for this project. Please advise.
|
|
Answer
|
Date:
|
1/30/2026 2:51:14 PM
|
|
This issue will be addressed via a forthcoming addendum. (Receipt of bids has been delayed.)
|
|
|
|
|
|
Question
|
|
Date:
|
1/22/2026 4:20:34 PM
|
|
We have not been able to find a supplier for Cement Treated Aggregate for this project. Please advise.
|
|
Answer
|
Date:
|
1/30/2026 2:51:01 PM
|
|
This issue will be addressed via a forthcoming addendum. (Receipt of bids has been delayed.)
|
|
|
|
|
|
Question
|
|
Date:
|
1/22/2026 4:20:33 PM
|
|
We have not been able to find a supplier for Cement Treated Aggregate for this project. Please advise.
|
|
Answer
|
Date:
|
1/30/2026 2:51:14 PM
|
|
This issue will be addressed via a forthcoming addendum. (Receipt of bids has been delayed.)
|
|
|
|
|
|
Question
|
|
Date:
|
1/22/2026 8:52:42 AM
|
|
Where exactly is the bridge incidentals temporary shoring located for line number 0380?
|
|
Answer
1 previous answer(s)
|
Date:
|
1/22/2026 11:12:11 AM
|
|
The bid item shall be used to protect the cattle guard on Parcel 004 during abutment excavation. If the Contractor's means and methods allow for work to proceed without the temporary shoring and do not violate excavation safety, it will be handled in accordance with the contract documents during construction.
|
|
|
|
|
|
Question
|
|
Date:
|
1/21/2026 10:04:14 AM
|
|
Given the extreme weather event in the forecast across the state this weekend and extending into next week, many contractors will be involved in snow removal activities across the state. It will be extremely difficult to receive proposals from suppliers and subcontractors, will the Department consider extending the letting date for bid submission?
|
|
Answer
|
Date:
|
1/21/2026 1:51:19 PM
|
|
We are monitoring the situation and will make any required adjustments early next week.
|
|
|
|
|
|
Question
|
|
Date:
|
1/21/2026 9:44:02 AM
|
|
Due to the extended distance and haul time from the closest ready mixed concrete plants, will the Department extend the discharge times for concrete for this project?
|
|
Answer
|
Date:
|
1/21/2026 10:01:12 AM
|
|
An extension to the discharge time will be granted provided the contractor submits a mix design with the appropriate admixtures and is approved by the department.
|
|
|
|
|
|
Question
|
|
Date:
|
1/19/2026 11:19:34 AM
|
|
Proposal Line Number 0380 is a pay item for Bridge Incidentals-Temporary Shoring. The grading and the bridge plans do not show Temporary Shoring. Where des the Department anticipate the contractor installing Temporary Shoring?
|
|
Answer
1 previous answer(s)
|
Date:
|
1/22/2026 11:12:34 AM
|
|
The bid item shall be used to protect the cattle guard on Parcel 004 during abutment excavation. If the Contractor's means and methods allow for work to proceed without the temporary shoring and do not violate excavation safety, it will be handled in accordance with the contract documents during construction.
|
|
|
|
|
|
Question
|
|
Date:
|
1/16/2026 3:33:40 PM
|
|
There appears to be a merged plan set within a single plan file.? Please clarify and rectify this issue.
|
|
Answer
|
Date:
|
1/16/2026 3:34:45 PM
|
|
This issue will be rectified via a forthcoming addendum.
|
|
|
|
|
|
Question
|
|
Date:
|
1/14/2026 4:46:35 PM
|
|
Due to allowable tolerances in the camber of the precast beams and the build-up from 2 layers of Kevlar on the beam joints, the epoxy overlay on the deck surface will not be uniform. Is it the Departments intention for the deck not to receive an asphalt overlay and for the epoxy waterproofing to be the final riding surface of the bridge?
|
|
Answer
|
Date:
|
1/21/2026 8:19:34 AM
|
|
See sheet 9 of the bridge plans for recommended sequencing and details. Build-ups due to the Kevlar are avoided by completing steps 3, 4, and 5 in the order prescribed.
|
|
|
|
|