Question
|
|
Date:
|
10/16/2025 5:36:22 PM
|
|
The work zone will occur behind temporary concrete barrier, which, in most locations, includes a travel lane and shoulder. The existing pavement in this area will become damaged due to heavy construction equipment. Is it the intent of the department that this asphalt be milled and paved at the contractor's expense or will this repair be paid under existing bid items 0890 Flexible Pavement Planing 0"-2" and 0350 Asphalt Concrete Ty. SM-12.5A?
|
|
Answer
|
Date:
|
10/20/2025 9:00:07 AM
|
|
The damage and repair of pavement in the work zone is the responsibility of the Contractor and at the Contractor's expense per Specification Section 105.
|
|
|
|
|
|
Question
|
|
Date:
|
10/15/2025 11:47:18 AM
|
|
The updated Form C-48, revised on 10-03-25, states "All vendors submitting a bid as a Prime Contractor shall complete and submit with their bids the following information as requested for (1) Subcontractor/Supplier Solicitation, and Utilization, and (2) for Vendor Survey." The note on page two of Notice 04, issued 10-10-25, states "The updated Form C-48 must be submitted in accordance with current specifications SP107-001510-04." Specification SP107-001510-04 states "Form C-48 must be received no later than 10:00 a.m. the next business day after the date and time stated in the Invitation for Bids, or the bid will be rejected as non-responsive." Does the completed Form C-48 need to be submitted with the bids (i.e. via Bid Express) or can it be submitted via email by 10:00 a.m. the next business day after bid opening?
|
|
Answer
|
Date:
|
10/15/2025 12:39:22 PM
|
|
Completed Form C-48 must be received no later than 10:00 a.m. the next business day after the bid letting, and can be submitted via email.
|
|
|
|
|
|
Question
|
|
Date:
|
10/15/2025 8:42:45 AM
|
|
Are the steel Sound Wall Posts eligible for the Steel Price Adjustment? These are incidental to item #910 - 519SD20-0005 Sound Barrier Wall Absorptive.
|
|
Answer
|
Date:
|
10/15/2025 11:08:46 AM
|
|
All items eligible for steel price adjustment are listed in the proposal. See SP109-000120-01.
|
|
|
|
|
|
Question
|
|
Date:
|
10/15/2025 12:19:41 PM
|
|
Yes, but the steel posts are not a pay item and are not listed, but they are a major cost. They are much more than any of the items listed. Are they not eligible for adjustment?
|
|
Answer
|
Date:
|
10/15/2025 3:07:55 PM
|
|
Per SP109-000120-01, only the items shown on Form C-21C are eligible for steel price adjustment on this project. No changes will be made to the C-21C form.
|
|
|
|
|
|
Question
|
|
Date:
|
10/13/2025 3:23:06 PM
|
|
Where is item # 890, Flexible Pavement Planing 0" - 2" to be used?
The plan sheets and details do not show this work.
|
|
Answer
|
Date:
|
10/15/2025 8:05:29 AM
|
|
Pay Item #890 - Flexible Pavement Planing 0"-2" is for the conditional post-traffic shift overlaying of I-264 WB between the Downtown Tunnel and the MLK Interchange (see Sheet 1H(9)). The contractor will need to assess the condition of the pavement and confirm with the Department if the overlay is needed.
|
|
|
|
|
|
Question
|
|
Date:
|
10/16/2025 5:21:54 PM
|
|
The end of the project is shown on the plans at sta. 262+72.71, which is a significant distance from the Downtown Tunnel. Based on your answer to the previous question, it appears the Flexible Pavement Planing will continue outside of the project limits. In addition, there appears to be no bid item for the new asphalt and pavement markings for re-paving this area. Please confirm that this is the intent and that it will be part of this contract.
|
|
Answer
|
Date:
|
10/20/2025 9:05:26 AM
|
|
No work is proposed beyond the project limit, Sta. 262+72.71.
|
|
|
|
|
|
Question
|
|
Date:
|
10/13/2025 3:08:23 PM
|
|
For the purpose of using the Predetermined Minimum Wage Rates for Portsmouth, VA, is this project classified as "Heavy" or "Highway"?
|
|
Answer
|
Date:
|
10/15/2025 8:03:40 AM
|
|
This project is classified as Highway.
|
|
|
|
|
|
Question
|
|
Date:
|
9/25/2025 12:16:04 PM
|
|
The link to the Revision of September 18, 2025, is not working. The following message is what appears when the link is accessed: 404 - File or directory not found.
The resource you are looking for might have been removed, had its name changed, or is temporarily unavailable.
Please fix this error.
|
|
Answer
|
Date:
|
9/25/2025 12:56:35 PM
|
|
Thank you. It can be seen now.
|
|
|
|
|
|
Question
|
|
Date:
|
10/6/2025 10:43:19 AM
|
|
While reviewing the sound barrier specification, we see no reference to "structure" mounted or "light weight" sound barrier wall segments. Are there any such walls specified for this project?
|
|
Answer
|
Date:
|
10/6/2025 11:54:51 AM
|
|
Neither “lightweight” nor “structure mounted” soundwalls are applicable to this project.
|
|
|
|
|
|
Question
|
|
Date:
|
9/11/2025 3:56:01 PM
|
|
SP108-000150-00 states that the Department will pay an incentive of $11,000 per calendar day the project meets the Substantial Completion requirements on or before the Substantial Completion Date. The incentive is capped at $660,000. If the Contractor does not achieve Substantial Completion on or before the Substantial Completion Date, the Department will assess a disincentive in the amount of $11,000 for each calendar day, including Sundays and Holidays, that the project does not meet the requirements of substantial completion as defined herein. There is no mention of a cap on the disincentive. Is the disincentive capped at a certain dollar amount?
|
|
Answer
|
Date:
|
9/15/2025 7:51:57 AM
|
|
As the provision reads in Section III, the $11,000.00 disincentive assessment will begin at midnight October 23rd, and will continue to be assessed each day until substantial completion is achieved. If Substantial completion is not achieved before the Fixed Com-pletion Date, liquidated damages shall be assessed concurrently with the Substantial Completion Disincentive. The disincentive amount is not capped.
|
|
|
|
|
Displaying questions 1 - 7 (of 7)