Project Info
Order Number UPC State Project Number Last Date to Post Questions
N10 122603 U000-107-174, B606 9/19/2025
Search Questions
Search
Question Type  
    The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered. Export Q&A    
Question List
Subject: Construction Surveying Type: Proposal
Question Date: 9/22/2025 8:57:01 AM
What is to be included in the price for Construction Surveying?  
Answer   Date: 9/22/2025 9:41:00 AM
Contractor should refer to Section 517 of the 2020 Road and Bridge Specifications for a description of Construction Surveying.  
 
Subject: reposting follow up questiuon Type: Other
Question Date: 9/19/2025 8:28:50 AM
In the event follow up question was not seen: Response does not provide sufficient clarification. For example: Is intent for face of wall sections A5 to be 2' 3 7/8" in front of face of footing /toewall? The field geometry of Abutment A does not match geometry shown on Plan Sheet B-10 or typical section shown on sheet B-9. With regards to plan sheet B-9 can you clarify the "varies" dimension and provide minimum and maximum heights and elevations of top of abutment footing / Toewall? What is directive if bench width at 2' below void is well less than 3' 0" detailed on plans? Can you also verify concrete quantities?  
Answer   Date: 9/22/2025 9:34:05 AM
At wall section A5 the dimension 2’-3 7/8” is from face of footing or toe-wall to face of proposed curtain wall. On sheet B-9 the “varies” dimension is dependent on the limits of excavation in the field, which shall be 2’ below bottom of existing void. Plan sheet B-9 call out 3’-0” (+/-). Contractor should adequately prepare the surface, after excavation, for pouring the concrete curtain wall. Concrete quantities were calculated based on dimensions in the plans provided.  
 
Subject: Annodes Type: Plan
Question Date: 9/10/2025 4:20:42 PM
Will annodes be required in the substructure repairs? If so how are they inteded to be paid?  
Answer   Date: 9/11/2025 8:56:07 AM
Anodes will not be required in substructure repairs.  
 
Subject: Plans Type: Plan
Question Date: 9/10/2025 1:32:37 PM
Shear studs are not available in a 41/2": length, please confirm if 4 11/16" or 4 3/16" is acceptable.  
Answer   Date: 9/15/2025 11:27:20 AM
4- 11/16" shear studs will be acceptable. A minor addendum will be forthcoming.  
 
Subject: CSX Railroad Type: Proposal
Question Date: 9/9/2025 9:00:04 AM
How many trains per day can be expected in this location?  
Answer   Date: 9/9/2025 10:08:01 AM
Estimated 8 day trains, 8 night trains, and 13 switching trains.  
 
Subject: Delayed Notice to Proceed Type: Proposal
Question Date: 9/8/2025 10:59:15 AM
Since the Railroad ROW agreement has been obtained will the department consider deleting the SP for delayed notice to proceed and allow the contractor to prosecute the work once the contract is executed?  
Answer   Date: 9/9/2025 8:08:49 AM
No. The contractor should bid on the proposal as is.  
 
Subject: Weight Limit Type: Plan
Question Date: 8/27/2025 10:35:46 AM
We are having difficulty locating under bridge access and meeting the 15ton weight limit, is there any allowances to be increased during construction? Will the weight limit remain the same after the new deck is poured on the structure? there are no requirements to remove the signs.  
Answer   Date: 8/27/2025 4:05:29 PM
The existing posting will not be removed or modified during construction. The bridge should be open to legal loads once the project is complete.  
 
Subject: Curtain Wall Construction Type: Plan
Question Date: 8/27/2025 10:29:44 AM
Plan Sheets B-9 and B-10 detail the proposed curtain wall, It does not however provide sufficient detail for the bottom of the proposed wall? Is the intent for the bottom of the wall to be 2' below the void under the footer? Is the intent for the bottom of this wall to be consistent or step up and down with the slope? Can an elevation be provided for the bottom of this wall?  
Answer   Date: 8/27/2025 4:05:11 PM
Excavation will be 2’ below the void under the footer. Curtain wall will be stepped to match the terrain.  
 
Question Date: 9/17/2025 9:30:58 AM
Response does not provide sufficient clarification. For example: Is intent for face of wall sections A5 to be 2' 3 7/8" in front of face of footing /toewall? The field geometry of Abutment A does not match geometry shown on Plan Sheet B-10 or typical section shown on sheet B-9 With regards to plan sheet B-9 can you clarify the "varies" dimension and provide minimum and maximum heights and elevations of top of abutment footing / Toewall? What is directive if bench width at 2' below void is well less than 3' 0" detailed on plans? Can you also verify concrete quantities?  
Answer   Date:
 
 
Subject: Railroad Type: Proposal
Question Date: 8/27/2025 10:26:05 AM
Without having the Railroad Right of Entry Agreement there are several items that need to be addressed. 1. What are the Limits/Requirements for necessary Railroad Insurance. 2. Who is responsible for obtaining and paying the railroad flaggers? 3. Will there be any required submittals for the Railroad? If so what will they be. 4.How many trains per days utilize this track? 5.Are ballast and track protection required, if so what are the limits? 6. Work will be required over the track, will equipment i.e. man lifts be allowed in the Railroad ROW?  
Answer   Date:
 
 
Subject: Existing Bridge Plans Type: Plan
Question Date: 8/26/2025 4:36:00 PM
Are existing bridge plans available? If so can they be posted?  
Answer   Date: 8/28/2025 7:45:04 AM
As-builts are now available.  
 