Advertisements
Division Home
Bid Results
Bid Tabs
Ad Report
VDOT Forms
Login Or Create Account
Project Info
Order Number
UPC
State Project Number
Last Date to Post Questions
M73
120522
0001-029-567, C501
5/23/2025
Search Questions
Search
Question Type
All
Plan
Proposal
Bid Sheet
Permits
Specifications
Other
Question Type must be selected.
The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered.
Export Q&A
Question List
Subject:
Proposal Line Number 0150 - REMOVE EXIST. AND SALVAGE EXIST. WIRELESS RADIO EQUIPMENT - 3 EA
Type:
Bid Sheet
Question
Date:
5/1/2025 3:37:28 PM
Proposal Line Number 0150 - REMOVE EXIST. AND SALVAGE EXIST. WIRELESS RADIO EQUIPMENT - 3 EA is not listed in the SUMMARY OF QUANTITIES and plans only call to REMOVE EXIST FLUIDMESH RADIO EQUIPMENT at two locations (Plan Sheet No 14A and 15A) that will be paid under pay item 0160 REMOVE EXIST WIRELESS RADIO EQUIPMENT - 2 EA. Please clarify the intent of pay item No 0150 - REMOVE EXIST AND SALVAGE EXIST WIRELESS RADIO EQUIPMENT - 3 EA
Answer
Date:
5/3/2025 1:57:06 PM
An addendum is forthcoming.
Subject:
Medium Haul SFP Module
Type:
Bid Sheet
Question
Date:
5/1/2025 3:17:31 PM
Plan sheet No. 3; CABLE AND JUNCTION BOX LEGEND No 1; calls to "... REPLACE EXISTING SFP TOWARD DMS 1760 WITH MEDIUM HAUL" There is no pay item for the Medium Haul SFP Module in the Schedule of Items, please clarify if you will add a pay item for the Medium Haul SFP Module or if this is a typo and will be a revision to the note in the CABLE AND JUNCTION BOX LEGEND in Plan sheet No. 3.
Answer
Date:
5/2/2025 10:57:53 AM
The pay item information on the SCHEDULE OF ITEMS sheet, as advertised, is accurate. An addendum is forthcoming with the revised plan sheets.
Subject:
3" RGS Conduit
Type:
Plan
Question
Date:
4/30/2025 11:36:40 AM
Call out G in plan sheets 8A, 10A, 10B, 11A, 12A, 14A and 15A is calling for 1-3" RGS. There is no pay item for 3" RGS but there is a pay item for CONDUIT METAL 2". Please clarify if this is a typo and you will revise the pay item to CONDUIT METAL 3".
Answer
Date:
4/30/2025 4:29:16 PM
The pay item information on the SCHEDULE OF ITEMS sheet, as advertised, is accurate. The Department will correct the specific callout on insertable sheets 8A, 10A, 10B, 11A, 12A, 14A and 15A. An addendum is forthcoming.
Subject:
Fiber Splice details
Type:
Plan
Question
Date:
4/30/2025 9:55:16 AM
Since no fiber splice details have been provided in the plans at a minimum can you please provide the fiber count for splice details E and F for sheet 16 and 17.
Answer
Date:
5/2/2025 1:28:34 PM
An addendum is forthcoming to include a Splicing and SFP Summary.
Displaying questions 1 - 4 (of 4)
Page:
1
First
Previous
Next
Last
Construction Advertisement Bulletin Board (CABB)
Update Profile
CABB v2.0
© 2008 Virginia Department of Transportation
3/14/2026 6:11:06 AM
2008