Subject: MOT Type: Plan
Question Date: 5/9/2025 12:32:20 PM
General Notes for Maintenance of Traffic state no lane closures can take place between 6:00am-9:00am and 3:00pm-6:30pm. Can the state please confirm the contractor is to prepare their bid according to this?  
Answer   Date: 5/9/2025 2:52:07 PM
Confirmed - no lane closures can take place between 6:00am-9:00am and 3:00pm-6:30pm on weekdays. Weekend work is allowable.  
 
Subject: Plan Type: Proposal
Question Date: 5/9/2025 12:21:02 PM
Will MOT stone be incidental or paid for under line item 150 25/26s. There will be significant amount of MOT stone to in order to construct the 6:1 wedge and re open traffic daily and safely. Thank you  
Answer   Date: 5/9/2025 2:51:06 PM
Please see "General Notes for Maintenance of Traffic" Note #3 on Plan Sheet 1E(1) regarding the payment for the wedge.  
 
Subject: Demo Parcel Type: Specifications
Question Date: 5/9/2025 8:57:28 AM
The Stantec report provided mentions "Wooden Shed Requiring Asbestos Inspection". Can the engineer confirm if asbestos report will need to be provided prior to demolition and if abatement is needed can pay item be added? Thank you  
Answer   Date: 5/9/2025 2:45:20 PM
Shed was inspected for asbestos and none was present. No asbestos report or pay item is required.  
 
Subject: Petroleum Contaminated Soil Type: Proposal
Question Date: 4/24/2025 7:47:08 AM
Can the department please provide the Stantec report for the contractor to evaluate and price petroleum contaminated soils? Thank you  
Answer   Date: 4/28/2025 11:55:56 AM
Both the HAZMAT and GeoTech reports are now available.  
 
Subject: Existing Utilities Type: Plan
Question Date: 4/15/2025 4:06:53 PM
Have the utilities been relocated? Plans depict fiber optic and underground telephone running the length of the job.  
Answer   Date: 4/16/2025 8:15:45 AM
Utility relocations are underway and are scheduled to be completed prior to award of the Contract.  
 