Advertisements   Division Home   Bid Results   Bid Tabs   Ad Report   VDOT Forms
Project Info
Order Number UPC State Project Number Last Date to Post Questions
M25 113848 0061-092-904, B652 5/23/2025
Search Questions
Search
Question Type  
    The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered. Export Q&A    
Question List
Subject: Traffic Signals Type: Specifications
Question Date: 5/21/2025 9:38:23 AM
Will the Department allow the use of trailer mounted portable traffic signals for this project?  
Answer   Date: 5/23/2025 8:14:29 AM
Yes, portable traffic signals for this project will be allowable.  
 
Subject: Rebar Splicer Bar Type: Plan
Question Date: 5/2/2025 1:37:57 PM
Plan Sheet 11 of 18 Construction Joint Detail shows Mechanical Splice. Are these the same as Rebar Splicer Bars shown in Bid Items 220, 230 and 240?  
Answer   Date: 5/5/2025 8:16:21 AM
The Mechanical Splice detail shown on Sheet #11 of the Plans is for the superstructure of the bridge. The quantities for splices on Sheet #11 are given on Sheet #2 under superstruc-ture quantities as "Reinforcing Steel Splicer (Bar Size #5)" and are represented by Proposal Line Number 0230. Proposal Line Number 0220 refers to splices in #4 bars in pier caps as shown on Sheet #6 of the Plans and Proposal Line Number 0240 refers to splices in #6 bars in abutment and pier seats as shown on Sheets 4-6 of the Plans.  
 
Subject: Cofferdam Type: Permits
Question Date: 4/25/2025 10:27:20 AM
The permit allows two cofferdam configurations. Cofferdam 1 and 3 allows for work at abutment A and Pier 1, while also allowing installation of the ACB in Span a. Cofferdam 2 allows for work at Abutment B and Pier 2, while also allowing installation of the ACB in Span c. All cofferdams are shown to be built through Span b. If the excavation in Span b and installation of ACB's in Span b are done per the permit and the dry there is not a permitted cofferdam configuration that allows this to be accomplished. Work could be performed in roughly two thirds of Span b but never where the cofferdam is built. How is the contractor to handle this permit and constructability restriction?  
Answer   Date: 4/30/2025 8:33:57 AM
Addendum forthcoming.  
 
Subject: Fixed completion date Type: Proposal
Question Date: 4/9/2025 8:08:33 AM
This project was delayed by two months from the original letting date, yet the fixed completion date did not change. Will the Department consider additional time for completion of this project?  
Answer   Date: 4/9/2025 9:30:37 AM
Yes, an addendum will be forthcoming.  
 
Question Date: 5/21/2025 11:40:37 AM
Will the completion date addendum be issued?  
Answer   Date: 5/22/2025 2:58:17 PM
Addendum has been posted. The Early Completion Incentive Only date is revised to September 3, 2026. Thank you.  
 

Displaying questions 1 - 4 (of 4)
Page: 1 First Previous Next Last