Advertisements
Division Home
Bid Results
Bid Tabs
Ad Report
VDOT Forms
Login Or Create Account
Project Info
Order Number
UPC
State Project Number
Last Date to Post Questions
M56
116198
0081-060-862, C501
6/20/2025
Search Questions
Search
Question Type
All
Plan
Proposal
Bid Sheet
Permits
Specifications
Other
Question Type must be selected.
The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered.
Export Q&A
Question List
Subject:
Conflicting construction
Type:
Other
Question
Date:
5/22/2025 3:04:55 PM
It appears the adjacent work at the New River bridge is ongoing. Will this project interfere with the Exit 105 work?
Answer
Date:
5/22/2025 3:06:03 PM
The work for the New River bridge is ongoing and has the potential to impact the work at Exit 105. VDOT is actively working to resolve the conflict and will advise once a resolution has been determined.
Question
Date:
6/18/2025 5:06:05 PM
Has VDOT determined a resolution? Is the bid still planning on letting next week?
Answer
Date:
6/19/2025 8:26:42 AM
Bid letting of the contract is still scheduled for next week.
Subject:
18" Jacked & Bored Pipe
Type:
Plan
Question
Date:
5/20/2025 12:02:29 PM
Is a 18" Steel Casing or 18" Stainless Steel Casing an acceptable material for the 18" Jacked & Bored Pipe.
Answer
Date:
5/22/2025 4:33:48 PM
An 18” smooth walled steel casing pipe is acceptable provided it has a minimum 0.5” wall thickness and meets all the provisions of the jack and bore special provision (SP302-000120-00).
Subject:
Time of Year Restriction for Clearing
Type:
Specifications
Question
Date:
4/21/2025 5:13:31 PM
Has the time of year restriction for tree clearing been given consideration to the fixed completion date for the project? The project will be awarded during the time of year restriction and the contractor will not be able to perform a significant portion of the clearing or the work that follows it until November 15th, 2025.
Answer
Date:
4/22/2025 11:35:55 AM
There is no TOYR for tree clearing if completed by 8/2/27 as per the permit. If the tree clearing is not completed by this date, the TOYR could be implemented.
Subject:
Bid Item 0030 18” Jacked & Bored Pipe
Type:
Bid Sheet
Question
Date:
4/21/2025 4:38:58 PM
The proposal references Spec. No. 302. However, there is a Jack and Bore SP302-000120-00 in the contract. One of the major differences is that the Contract SP INCLUDES ALL OBSTRUCTIONS. 1. Which specification applies to the contract pay item. 2. Are obstructions to be included in the bid unit price? 3. Is rock considered to be an obstruction? Or will it be paid per the VDOT Standard Specification 302?
Answer
Date:
4/23/2025 9:24:45 PM
SP302-000120-00 notes that the item includes all costs including obstructions. Rock would be considered an obstruction and should be included int the cost.
Subject:
Rockfall Temporary Protection Fence
Type:
Bid Sheet
Question
Date:
4/16/2025 1:57:46 PM
On sheet 2C of the plans, it says that there is 850 LF of Temporary fence. Pay item 450 only has a quantity of 10 LF. Please advice what the correct amount of Fencing that is required.
Answer
Date:
4/17/2025 12:11:36 PM
Please bid in accordance with the advertised documents.
Subject:
Pavement Removal
Type:
Bid Sheet
Question
Date:
4/16/2025 1:17:10 PM
For the 4.5 foot wide shoulder strengthening work the hatching on the plan sheets denote Demolition of Pavement. The MOT typical sections call out 12" Flexible Pavement Planing. There are pay items for 0470 Demolition of Pavement Flexible & 0640 Flexible Pavement Planing Above 4". Please confirm what pay item the department intends to use to pay for the 12" pavement removal for the 4.5 foot shoulder widening.
Answer
Date:
4/17/2025 12:11:47 PM
Please bid in accordance with the advertised documents.
Subject:
Inset D
Type:
Plan
Question
Date:
4/11/2025 3:20:04 PM
Inset D on 9981-060-862 Plan Sheet 2A(2) for station 28+50 to 38+50 shows existing grade, an unlabeled section, a layer of geotextile fabric, 20" of dry riprap class A1, and 6" No. 1 aggregate. No where in the cross sections from existing grade to the proposed finish grade is it greater than 2'. In some cases it is 1 foot or less. Does the department intend for the existing ditch to be excavated to install the proposed section or geotextile placed on the existing ditch, 20" of dry riprap class A1 and 6" of No. 1? This second option would raise the proposed grade from what is indicated on the cross section. There is no indication of excavation in the cross sections. Any excavation in this area would likely be rock. Please clarify.
Answer
1 previous answer(s)
Date:
4/14/2025 3:55:54 PM
The intent is to have a minimum of 20” of rip rap in the existing ditch bottom separated by a geotextile fabric and then topped by 6” of #1 aggregate. No excavation is required. A plan revision will be forthcoming via addendum.
Subject:
Amendment Plans
Type:
Other
Question
Date:
4/11/2025 11:57:13 AM
Please confirm when you have posted the Amendment Plans.
Answer
Date:
4/11/2025 11:59:47 AM
The revised files are now available. The merged sets were revised as well.
Subject:
Storm Drain
Type:
Plan
Question
Date:
4/11/2025 10:52:35 AM
At exit 94 SB storm drain pipe 4-4 to 4-3 on plan view on sheet 4 shows a pipe size of 18". The profile on sheet 6 and drainage description on sheet 3B shows a pipe size of 15". Please confirm the correct pipe size.
Answer
Date:
4/11/2025 4:06:55 PM
The correct pipe size is 18”. An addendum will be forthcoming.
Subject:
rock face tree removal
Type:
Other
Question
Date:
4/11/2025 10:49:25 AM
Will VDOT consider the required tree removal on the rock face for the rockfall drape scope to be specialty work? Can we use a subcontractor who is not prequalified with VDOT to perform this work?
Answer
1 previous answer(s)
Date:
4/14/2025 3:15:13 PM
It's been determined that this work will not be considered as specialty work; however, all subcontractors must still be qualified.
Displaying questions 1 - 10 (of 15)
Page:
1
2
First
Previous
Next
Last
Construction Advertisement Bulletin Board (CABB)
Update Profile
CABB v2.0
© 2008 Virginia Department of Transportation
3/13/2026 8:22:44 AM
2008