Question List
Subject: Sound wall pay quantity Type: Proposal
Question Date: 11/11/2022 10:00:43 AM
There appears to be a significant difference between the sound wall pay quantity and the quantities detailed in the contract plans. Please verify the bid quantity for sound walls is correct  
Answer   Date: 11/11/2022 1:45:52 PM
The sound wall quantity provided includes the amount required to square off the bottom of the wall and provide 6" minimum embedment where the ground line isn't flat between post locations. Embedment is required per VDOT Specifications Section 519.03(c)3 and shown on Sheet 21(36).  
 
Subject: Sound Wall Stain Type: Specifications
Question Date: 11/11/2022 9:58:05 AM
Are the sound walls stained uniformly with one color?  
Answer   Date: 11/11/2022 11:14:10 AM
According to the Special Provision for Sound Barrier Walls Aesthetic Finishes Special Provision, the color stain system is designed to duplicate the appearance of standard architectural designs. Please see the Special Provision for additional details regarding color stain coating.  
 
Question Date: 11/11/2022 9:58:02 AM
Are the sound walls stained uniformly with one color?  
Answer   Date:
 
 
Subject: Sound Wall Posts Type: Plan
Question Date: 11/10/2022 12:55:40 PM
If the contractor elects to use concrete posts for the sound walls, are they required to be fully embedded in the drilled shafts as with the steel posts? If not, what is the minimum embedment depth required?  
Answer   Date: 11/10/2022 4:12:12 PM
If concrete posts are used, they shall be embedded by about 6’ into the drilled shafts. The exact embedment depth will be determined by the post fabricator. Note that if concrete posts are used, the drilled shaft will then need to be reinforced by rebars (minimum 1% reinforcement) per note on Sheet 21(36). This is consistent with VDOT Road and Bridge Specification Section 519.01.  
 
Subject: Sequence of Construction Type: Plan
Question Date: 11/9/2022 9:41:26 AM
Plan Sheet 1H(1) details the planned sequence of construction for the work along I-264 to Construct the Sound Barrier Walls. The work requires us to install barrier, E&S Controls / clearing and grading and then complete ITS & Lighting work at each of the 9 wall locations prior to starting the wall work. Are we restricted to working at one location at a time or can we work in multiple locations provided we get the ITS & Lighting accepted by VDOT before starting wall work?  
Answer   Date: 11/9/2022 10:48:15 AM
The plans do not intend to limit the Contractor to work in one location at a time. It's the Contractor's discretion to establish multiple work zone locations at the same time while meeting the MOT Plan and requirements of the VWAPM for sign and temporary traffic control device spacings.  
 
Subject: Drainage EW-1 payment Type: Bid Sheet
Question Date: 11/5/2022 10:21:55 AM
The draiange table and plans depict several Endwalls (EW-1) but there is no pay item for the endwalls shown. Are the endwalls incidental to other pay items or should there be a pay item for the endwalls?  
Answer   Date: 11/7/2022 4:11:03 PM
Per VDOT R&B standard 101.01, EW-1’s are paid for by “cubic yards of concrete”. More specifically, they are included with the quantities for Pay Item 00525 Concrete Class A3 Misc.  
 
Question Date: 11/5/2022 10:21:53 AM
The draiange table and plans depict several Endwalls (EW-1) but there is no pay item for the endwalls shown. Are the endwalls incidental to other pay items or should there be a pay item for the endwalls?  
Answer   Date:
 
 
Subject: Request for Geotechnical Engineering Report Type: Specifications
Question Date: 9/26/2022 9:19:41 AM
In the special provision section 519 SOUND BARRIER WALLS and plan sheet 21 there is reference to the Geotechnical Engineering Report. However, it was not provided in the bidding documents. Please consider this a request that the Geotechnical Engineering Report be made available to the bidders.  
Answer   Date: 9/26/2022 12:42:37 PM
The Geotech report is now available for the contractors to view.  
 

Displaying questions 1 - 6 (of 6)