Question
|
|
Date:
|
7/20/2026 5:58:05 PM
|
|
Please confirm the strand nominal size and guaranteed ultimate tensile strength for that strand that was used in those girders. This information may be required for the design of the CFRP Strengthening.
|
|
Answer
|
Date:
|
7/22/2026 2:24:15 PM
|
|
The contract documents do not identify the nominal strand size or guaranteed ultimate tensile strength of the existing prestressing strand. Available information for CFRP design verification is contained in the existing as-built plans. Bidders shall base their bids on the contract documents as issued and design the CFRP system to meet the minimum design requirements shown on the plans.
|
|
|
|
|
|
Question
|
|
Date:
|
7/20/2026 4:31:18 PM
|
|
Please specify the limits of responsibility of the delegated design Engineer for the CFRP system. It is our understanding that this responsibility is limited to converting failed strand capacity into CFRP capacity, but VDOT retains the EOR role when it comes to definition of the repair locations and extent of the strengthening to be applied. Please confirm.
|
|
Answer
|
Date:
|
7/22/2026 2:23:34 PM
|
|
Confirmed. The delegated design Engineer’s responsibility is limited to designing the Contractor’s CFRP system to satisfy the minimum design requirements shown in the contract documents. The repair locations, repair limits, and required strengthening extents are established by the contract plans and remain the responsibility of the Department/Engineer of Record.
|
|
|
|
|
|
Question
|
|
Date:
|
7/20/2026 4:30:24 PM
|
|
Per CFRP Repair Notes on Sheet 6, “Estimated number of layers in the Beam Design Table are for bid purposes only…” Should all bidders using CFRP products with material properties that are equal or greater to the properties listed on Sheet 6 base their bids on the CFRP widths and number of layers shown in the Beam Design Table?
|
|
Answer
|
Date:
|
7/22/2026 2:22:46 PM
|
|
Yes. For bidding purposes, all bidders shall base their bids on the CFRP dimensions and estimated number of layers shown in the Beam Design Table. As noted on Sheet 6, those values are for bid purposes only, and bidders may furnish CFRP products with different design properties, provided the specified minimum design requirements are satisfied. No additional compensation will be made for additional layers required by the Contractor’s selected system beyond the estimated number shown for each design case in the Contract Plans.
|
|
|
|
|
|
Question
|
|
Date:
|
7/20/2026 3:11:18 PM
|
|
Please clarify number and types of tests. Plan sh 6 Pull-Off Test notes state in addition to the Test Beam, the contractor shall perform a minimum of 3 tests and at least 1 per 1000 SF of CFRP (approximately 29 EA based on bid quantity). In addition, 3 EA for areas a & b, and 2 EA for areas c, d, e & f (14 EA at a minimum). Are these 14 EA location specific tests in addition to the 29 EA tests and Test Beam tests? Or are the location tests specifying where the 29 EA test are to be performed?
|
|
Answer
|
Date:
|
7/22/2026 2:20:24 PM
|
|
The location-specific tests identify the minimum required distribution of the production pull-off testing and are not additional to the overall minimum frequency requirement.
|
|
|
|
|
|
Question
|
|
Date:
|
7/20/2026 3:12:18 PM
|
|
Typical Section plan sh 5 shows precast prestressed monolithic superstructure, however most spans observed have a typical composite deck section with AASHTO beams. The as-built drawings do not provide specific locations/spans where each beam type may be found. Please confirm which type of beams are present in the repair areas and revise the typical section and repair plans appropriately.
|
|
Answer
|
Date:
|
7/22/2026 2:21:20 PM
|
|
The contract plans govern for bidding purposes. Repairs are intended for the select beams identified in the contract documents, and existing conditions/configuration in the repair areas shall be field verified with any discrepancies brought to the Engineer’s attention prior to proceeding.
|
|
|
|
|
|
Question
|
|
Date:
|
7/20/2026 3:09:24 PM
|
|
Referencing the CFRP Repair notes (pp5) and Waterproofing notes (pp4) on plan sh 6, it is not clear which concrete surfaces require cleaining/prepping. Please confirm if the complete concrete beam surfaces receiving repairs are to be cleaned/prepped or only the limits receiving CFRP and/or concrete repairs are to be?
|
|
Answer
|
Date:
|
7/22/2026 2:37:14 PM
|
|
Refer to the limits shown on Contract Plan Sheet 7 for the required extents of CFRP application and waterproofing. Surface preparation and cleaning shall be performed in accordance with the applicable notes and specifications within those limits.
|
|
|
|
|
|
Question
|
|
Date:
|
7/20/2026 3:10:30 PM
|
|
Plan sh 8 notes additional prep may be required for voids and hardened waterproofing material. How will the additional prep/grinding and patching be compensated? If not compensated, under what item is it incidental to?
|
|
Answer
|
Date:
|
7/23/2026 10:22:04 AM
|
|
All additional prep work that may be required, including but not limited to grinding, void filling, patching, and hardened waterproofing material removal, is incidental to the "Br. Superstr. Wid./Repair, Fiber Reinforced Polymer Wraps Spr. Struct. (Virginia Str. No. 1901)" pay item. Contractors should account for these anticipated conditions in their unit price bid for that item. A revision is forthcoming.
|
|
|
|
|
|
Question
|
|
Date:
|
7/20/2026 3:09:59 PM
|
|
Referencing the CFRP Repair notes (pp10-12) and Waterproofing notes (pp4) Is EP-3T only required over CFRP and EP-3T/EP-3B required on the unwrapped concrete repairs? Additionally, do the full beams get epoxy coating or only CFRP/concrete repair sections?
|
|
Answer
|
Date:
|
7/22/2026 2:38:06 PM
|
|
EP-3T is required on the exposed CFRP surfaces, with a minimum of two coats, while EP-3T/EP-3B epoxy is required on the exposed beam concrete surfaces. Waterproofing epoxy EP-3T/EP-3B shall be applied in accordance with the limits shown on Sheet 7 of the Contract Plans, regardless of whether the surface is existing or repaired concrete.
|
|
|
|
|
|
Question
|
|
Date:
|
7/20/2026 2:44:56 PM
|
|
Are there any limitations on size of individual concrete repairs or affected regions to be repaired at any given time? Can all the concrete repairs be done at once or need to phased?
|
|
Answer
|
Date:
|
7/22/2026 2:17:48 PM
|
|
Refer to the repair limits shown on Contract Plan Sheet 7 and the Concrete Repair Notes on Contract Plan Sheet 8 for the applicable limitations and sequencing requirements.
|
|
|
|
|
|
Question
|
|
Date:
|
7/17/2026 7:46:40 AM
|
|
Is there a minimum qualifications/experience/certification requirement for the CFRP installation company and its crew performing the work in the field? Please elaborate on who will be authorized to actually perform the installation of this system?
|
|
Answer
|
Date:
|
7/22/2026 2:14:48 PM
|
|
The Contractor shall meet the qualification requirements specified in Section 412.03(s) of the VDOT Road and Bridge Specifications for performing Fiber Reinforced Polymer Wrap installation.
|
|
|
|
|
|
Question
|
|
Date:
|
7/17/2026 7:43:51 AM
|
|
I do not see any anticipation for repairs at the Bridge bearing areas of the girders... From experience, these are very susceptible to have extensive damage also. The contract plans have no provisions for Jacking and blocking if such events occur, what is the department contingency and plan of operation if such situations arise? Without a plan approved from start there is a great potential for delays if such events are treated as change orders on a one by one basis... Please explain how such risk will be mitigated?
|
|
Answer
|
Date:
|
7/22/2026 2:15:46 PM
|
|
Repairs within the bearing areas requiring jacking and blocking of the superstructure are not within the scope of work for this contract, as clarified by the repair limits on sheet 7.
|
|
|
|
|
|
Question
|
|
Date:
|
7/17/2026 7:36:47 AM
|
|
Will the department allow the use of under bridge suspended platforms for this work? Any specific conditions to their use on this project?
|
|
Answer
|
Date:
|
7/22/2026 2:16:45 PM
|
|
Under-bridge suspended platforms are permitted, provided they comply with all applicable Contract requirements. These include, but are not limited to: (1) the Construction Access Special Provision Copied Note; (2) the scheme and schedule of operations requirements in the 8th paragraph under the General Notes on Contract Plan Sheet 3; (3) submission of a PE-certified attachment plan, if the platform is attached to the structure, in accordance with the 5th paragraph under the General Notes on Contract Plan Sheet 4; (4) the prohibition on performing work from the bridge deck per the 3rd paragraph under the General Notes on Contract Plan Sheet 3; (5) maintenance of the required navigation clearances per the 2nd paragraph under the General Notes on Contract Plan Sheet 4; and (6) the Coast Guard notification requirements in the 8th paragraph under the General Notes on Contract Plan Sheet 3.
Bidders shall account for these requirements in their construction access planning and bid.
|
|
|
|
|
|
Question
|
|
Date:
|
7/16/2026 4:56:53 PM
|
|
Plan No. 235-080, Sheet 6 of 10, states that "No additional compensation shall be made to the Contractor for additional layers that go beyond the estimated number of layers for the Design Case, per the Beam Repair Design Table."
Please clarify how the FRP will be measured and paid if final calculations performed using the specified design criteria and approved FRP material properties, and the design demonstrates that more FRP layers or quantity than the estimated quantity in Bid Documents is required. Specifically, clarify:
a. Whether the Contractor will be directed to install the additional FRP to met final design/approved calculations?
b. How the additional layers will be measured and the Contractor compensated?
|
|
Answer
2 previous answer(s)
|
Date:
|
7/23/2026 10:21:43 AM
|
|
The CFRP design was developed based on the assumed number of lost prestressing strands identified through the hands-on inspection and conservative assumptions based on experience from the Phase I repairs. Therefore, it is not anticipated that the final design will require more CFRP layers than those shown in the Contract Plans. Measurement and payment for Fiber Reinforced Polymer Wrap shall be in accordance with the Special Provision Copied Note titled "SECTION 412—WIDENING, REPAIRING, AND RECONSTRUCTING EXISTING STRUCTURES," which defines the basis of measurement and payment for this work. A revision is forthcoming.
|
|
|
|
|