Project Info
Order Number UPC State Project Number Last Date to Post Questions
A11 113535 0017-034-911, B646, C501 8/21/2026
Search Questions
Search
Question Type  
    Export Q&A    
Question List
Subject: Bridge Girders Type: Other
Question Date: 7/17/2026 7:38:47 AM
For the Bridge Girders, an answer was posted about the structural steel required as follow, “The structural steel is required to be both Grade 50W and painted. All surfaces shall be painted (other than the anchor bolts, as called out in the plans.” Please Clarify the VDOT “painted requirement”, it is not that clear reading through the different specs, if it will be sufficient a shop painted with a primer and also the Girders will need any Field Coating.  
Answer   Date:
 
 
Subject: Ref No. 1330 Temporary Signs Type: Bid Sheet
Question Date: 7/16/2026 6:50:35 PM
Please confirm the quantity for bid item REF 1330 temporary sign. The addendum #4 quantity provided in the bid item list does not appear to match the total between the two plan sets.  
Answer   2 previous answer(s) Date: 7/17/2026 1:15:50 PM
An addendum is forthcoming to address this.  
 
Subject: Deck Drainage System plans Type: Plan
Question Date: 7/16/2026 3:28:27 PM
About the Deck Drainage System plans subject; a question was answered about a revised sheet 19 that would be included in the next addendum. That sheet 19 didn’t come with any revision on the last addendum. It is very important to provide more detail and more information about this whole System. Please resolve accordingly.  
Answer   Date: 7/17/2026 11:32:29 AM
An addendum is forthcoming.  
 
Question Date: 7/14/2026 8:08:33 AM
It appears that Addendum #4 did not address this, will another addendum be released?  
Answer   Date: 7/17/2026 11:29:36 AM
An addendum is forthcoming.  
 
Question Date: 6/15/2026 2:28:16 PM
Please provide plans of the Deck Drainage System as indicated in the special provisions and a Bid Item, NS DECK DRAINAGE SYSTEM STR. NO. 1078  
Answer   Date: 6/18/2026 4:17:31 PM
Details and locations for the Deck Drainage System are shown on Sheets 14 and 19. Sheet 19 has been revised to more clearly identify the deck drain locations on the Deck Plan. The revised sheet will be included in the next addendum.  
 
Question Date: 7/14/2026 8:08:33 AM
It appears that Addendum #4 did not address this, will another addendum be released?  
Answer   Date: 7/17/2026 11:29:36 AM
An addendum is forthcoming.  
 
Subject: Bridge Stages Type: Plan
Question Date: 7/13/2026 2:47:10 PM
After reviewing traffic control and plan sheets, is there a specific reason as to why the Bridge is being constructed in stages? Can the construction of the Bridge be done in a single stage or elements done in a single stage? (E.G. – Substructure single stage, Concrete superstructure two stages)  
Answer   Date: 7/15/2026 7:50:11 AM
The intention of separating the bridge into two stages is to reduce concrete cracking. The Contractor will be required to construct the substructure and deck in two stages as shown in the plans.  
 
Subject: Revised Plan Sheets Type: Plan
Question Date: 7/13/2026 11:13:41 AM
In Project Wise there are R3 Plan Sheet revisions that are associated with the July 10, 2026 Addendum. In addition there are R1 and R2 Plan Sheet revisions that are not referenced or mention anywhere. Are R1 and R2 Plans sheets suppose to be part of this Contract and where/when were they added to the Contract Documents. Please advise  
Answer   1 previous answer(s) Date: 7/17/2026 1:17:13 PM
This project has been delayed and we will release official notices of all plan changes.  
 
Question Date: 7/13/2026 2:10:34 PM
No addendum was received notifying contractors of the R1 and R2 plan sheet revisions posted to the ProjectWise site. Are R1 and R2 Plan sheet revisions part of the contract documents? If so, please issue another addendum formally adding them to the contract and also allow additional time to the bid for contractors to the review the 53 additional plan sheets and prepare a responsible bid.  
Answer   1 previous answer(s) Date: 7/17/2026 1:16:42 PM
This project has been delayed and we will release official notices of all plan changes.  
 
Subject: Revised Plan Sheets Not Released on ProjectWise Type: Plan
Question Date: 7/13/2026 8:07:32 AM
The revised plan sheets referenced in the July 10th revision letter are currently not showing up on ProjectWise. Please release them.  
Answer   Date: 7/13/2026 9:42:50 AM
Revised plan sheets have now been posted.  
 
Question Date: 7/13/2026 9:54:09 AM
The file posted this morning still does not contain any of the referenced plan sheets  
Answer   Date: 7/14/2026 11:13:24 AM
The referenced plans are now available.  
 
Subject: Bid Date Type: Other
Question Date: 7/10/2026 9:03:39 AM
Will VDOT consider an extension of the bid due date; the next revision to the plans has not been received yet which will take significant time for contractors to review and incorporate into the bids?  
Answer   1 previous answer(s) Date: 7/20/2026 1:16:21 PM
Due to the this revision including some extra sheets (R1 & R2), but not answering all questions, VDOT will delay bid-letting and issue another addendum in the next week to summarize ALL plan changes.  
 
Subject: Revisions from last month Type: Other
Question Date: 7/8/2026 1:40:29 PM
Will you consider delaying this project? There are several plan revisions that have not been posted and the contractors will need time to review and price accordingly.  
Answer   1 previous answer(s) Date: 7/20/2026 1:17:17 PM
Due to this revision including some extra sheets (R1 & R2), but not answering all questions, VDOT will delay bid-letting and issue another addendum in the next week to summarize ALL plan changes.  
 
Subject: Existing Bridge Demolition Type: Other
Question Date: 6/26/2026 8:28:14 AM
Existing bridge demolition is not shown to occur until phase 7 of the TMP. If the new interchange is open to traffic in its final configuration and all other requirements for substantial completion are met, will VDOT permit the existing bridge demolition to occur after the substantial completion date?  
Answer   Date: 7/1/2026 7:48:14 AM
The bridge demolition will need to be completed in order to meet the final grading and permanent seeding requirements of substantial completion.  
 
Subject: Substantial Completion Date Type: Other
Question Date: 6/26/2026 8:05:48 AM
With the delay to the bid date will VDOT considered pushing back the Substantial Completion date for the project?  
Answer   Date: 7/2/2026 2:42:17 PM
The CTDR is currently being revised with the new let date. VDOT will likely consider pushing back the Substantial Completion date with this delay. VDOT will confirm once we have the revised schedule.  
 

Displaying questions 1 - 10 (of 76)