Order Number
UPC
State Project Number
Last Date to Post Questions
N96
121244
0081-086-750, B664-B667, B675-B676, N501
3/20/2026
Search Questions
Search
Question Type
All
Plan
Proposal
Bid Sheet
Permits
Specifications
Other
Question Type must be selected.
The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered.
Export Q&A
Question List
Subject:
Surface Repairs
Type:
Proposal
Question
Date:
3/23/2026 11:21:23 AM
Will substructure surface repairs (piers/columns/abutments) and superstructure surface repairs (not assoicated with beam ends/seats) be permitted during unrestrictured daytime hours wihtout closing I-81?
Answer
Date:
3/23/2026 12:21:08 PM
Substructure surface repairs (piers/columns/abutments) and superstructure surface repairs not associated with beams or seats will be permitted during unrestricted daytime hours without closing I-81. Traffic will not be allowed in lanes above beam repairs at any location along the span and beam seat repairs that result in a loss of bearing area.
Subject:
Lane Closure
Type:
Proposal
Question
Date:
3/23/2026 10:05:20 AM
Please confirm that a single lane on I-81 can be continuously closed from Sunday night at 7:00 PM through Friday morning at 7:00 AM, between Labor Day through Memorial Day.
Answer
Date:
3/23/2026 11:00:08 AM
Yes, a single lane on I-81 can be continuously closed from Sunday night at 7:00 PM through Friday morning at 7:00 AM, between Labor Day through Memorial Day.
Subject:
Superstructure surface repars / beam end repairs
Type:
Bid Sheet
Question
Date:
3/20/2026 3:52:01 PM
Can VDOT consider adding a separate bid item for beam end repairs to be measured and paid per each (EA), as is typical on VDOT projects, rather than including them under superstructure surface repair (SY)? Beam end repairs require individualized formwork, involve confined access and complex geometry, and are significantly more labor-intensive than typical surface repairs. Due to the small surface area at each location, payment by SY does not appear to adequately account for the effort and cost required.
Answer
Date:
3/20/2026 5:15:14 PM
VDOT will not change the pay items at this time.
Subject:
Work Hours
Type:
Specifications
Question
Date:
3/20/2026 2:47:51 PM
Can VDOT explain the allowable work hours? Page 12 conflicts with the Table on Page 183. Will 24-hour lane closures be permitted at all on I-81 on this project as shown on Page 183?
Answer
Date:
3/23/2026 9:05:49 AM
Lane closures on I-81 are as follows: Labor Day through Memorial Day, Contractor may close a single lane five days a week beginning 7:00 PM Sunday through 7:00 AM Friday. Lane closure must be removed by 7:00 AM Friday. Memorial Day through Labor Day, single lane closures are only permitted from 7:00 PM to 7:00 AM, 12 continuous hours, Sunday through Thursday. Lane closure must be removed by 7:00 AM every morning. Lane closures are not permitted on Friday or Saturday.
Subject:
Jacking & Blocking of Beams
Type:
Other
Question
Date:
3/19/2026 8:18:57 AM
Will the Jacking & Blocking of the Bridge Beams be permitted by jacking at the Beam Diaphragm?
Answer
Date:
3/19/2026 9:00:02 AM
Jacking and blocking will be permitted at the diaphragm per the detail provided in the NPA.
Subject:
Lane Closure
Type:
Other
Question
Date:
3/18/2026 8:35:29 AM
Would the use of a Stationary Lane Closure of one lane in each direction simultaneously on SR 622 with the proper Traffic Control Devices be permitted?
Answer
Date:
3/20/2026 9:33:48 AM
The Department may authorize closures on Route?622 once the contractor submits and obtains approval of a detailed plan of operations for this area. The plan must clearly identify the specific work to be performed during each closure, the necessary closure durations, and an appropriate MOT plan. A full-time closure for the entire duration of the project will not be allowed.
Subject:
Type C Patching
Type:
Specifications
Question
Date:
3/18/2026 8:16:33 AM
Please provide clarification on the requirement noted below; "TYPE C PATCHING (VES) Type C Patching (VES) for full depth deck repairs shall be performed in accordance with Section 412.03(b) of the Specifications except replacement concrete shall be Latex Modified (VES)." Just to clarify the intent of this note is to require the use of LATEX MODIFIED (VES) for the concrete patch material?
Answer
Date:
3/18/2026 9:55:53 AM
Yes, the intent of the note is to require the use of LATEX MODIFIED (VES) for the concrete patch material.
Subject:
N96 Bridge Locations
Type:
Proposal
Question
Date:
2/24/2026 3:14:44 PM
In using the VDOT Bridge Location Map Site, we have locate VA Bridge #2020-2023 (assuming these are old #B666-B667 & B675-B675). We have been unable to account for VA Bridge #2018 #2019 (B664 & B665). Based on only 2 mobilizations shown for this project rather than 3, along with the as-built drawings for bridge over SR 622 which separates the bridge as "Over Rte. 622 & Nick's Creek" with different numbers it would appear that VA #2018 & #2019 are the same as VA #2020 & #2021. Please review and confirm this as correct and if not please provide the accurate location for VA Bridge #2018 # #2019
Answer
Date:
2/27/2026 11:56:43 AM
Bridge numbers 2018 and 2019 are the ramp bridges adjacent to bridges 2020 and 2021.
Subject:
Plans?
Type:
Plan
Question
Date:
2/13/2026 12:31:51 PM
Is this a no plan project? It looks like only As Builts are available in ProjectWise.
Answer
Date:
2/13/2026 12:37:35 PM
Yes, this is a no-plan project. The no-plan assembly is included as part of the proposal.
Displaying questions 1 - 9 (of 9)
Page:
1
First
Previous
Next
Last
Construction Advertisement Bulletin Board (CABB)
Update Profile
CABB v2.0
© 2008 Virginia Department of Transportation
4/15/2026 3:44:09 AM
2008