A01
122877
0019-095-123, C501
3/20/2026
Search Questions
Search
Question Type
All
Plan
Proposal
Bid Sheet
Permits
Specifications
Other
Question Type must be selected.
The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered.
Export Q&A
Question List
Subject:
Time of Year Restriction
Type:
Proposal
Question
Date:
3/17/2026 11:58:45 AM
Will the Time Of Year restriction be enforced on this contract ,Seeing that the Execution date of the contract will falls after April 1st cut off date ?
Answer
Date:
3/17/2026 4:55:31 PM
Environmental restrictions including a tree cutting from April 1st till November 15th will be enforced. Tree trimming activities on Everett Hagy Road are anticipated in phase 4 of the proposed Sequence of Construction as provided in the plan set. This activity is not expected to cause any delays in meeting the project completion date.
Displaying questions 1 - 1 (of 1)
Page:
1
First
Previous
Next
Last
Construction Advertisement Bulletin Board (CABB)
Update Profile
CABB v2.0
© 2008 Virginia Department of Transportation
4/15/2026 3:49:08 AM
2008