Project Info
Order Number UPC State Project Number Last Date to Post Questions
568 127805 PM5Q-046-F26, P401 1/30/2026
Search Questions
Search
Question Type  
    The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered. Export Q&A    
Question List
Subject: AGR.BASE MAT.TY.I OR II NO. 21A OR 21B Type: Proposal
Question Date: 1/30/2026 2:29:00 PM
Rte. 711 has 677 Tons of Agr. Base Mat. Ty. I OR II 21A or 21B . Could the department please detail a little more on the intent for this material? Grace Street has 80 tons for the replacement of unsuitable material. Is this 677 tons to be used as replacement for unsuitable or shoulder stone for the entire project or something totally different?  
Answer   Date: 2/2/2026 9:10:26 AM
The Agr. Base Mat. Ty. I OR II 21A or 21B is to be used as needed to replace any unsuitable material encountered in the field.  
 
Subject: Asphalt Indice Price Type: Proposal
Question Date: 1/28/2026 4:21:10 PM
With the bid letting being delayed from 1/28/26 to 2/4/26, are Contractors supposed to use the January or February Asphalt Indice Price?  
Answer   Date: 1/28/2026 4:41:36 PM
The Base Index and base index price for this contract will be those published on the Construction Division website for the month of January. An addendum will be posted by noon 1.29.2026 to add the spcn accordingly.  
 
Subject: Plan Type: Plan
Question Date: 1/21/2026 10:44:53 AM
Is the curb and gutter just an allowance for replacing broken curb or is there specific area there will be curb and gutter replacement. Thank you  
Answer   Date: 1/21/2026 3:00:22 PM
The contractor is responsible for preserving and protecting existing curb and gutter. Any damages to the curb and gutter caused by the Contractor’s operations will be the responsibility of the Contractor to be repaired at no cost to the Department. The Curb and Gutter line item is to be used as needed at the direction of the Engineer.  
 
Question Date: 1/21/2026 10:33:45 AM
What manhole/utility demo plan is the department referring to? It looks like we are to just adjust existing utilities.  
Answer   Date: 1/21/2026 3:02:28 PM
The manhole/utility demo plan shall clearly define the proposed method for performing resurfacing work around existing utility structures and procedures for demolition and reconstruction of manholes, if required.  
 
Question Date: 1/21/2026 10:27:56 AM
Extensive potholing will need to be performed on Grace Street. Is this cost to be incidental to all other construction items?  
Answer   Date: 1/21/2026 2:58:19 PM
Yes, potholing will be incidental to appropriate bid items.  
 
Subject: Trench Milling Type: Bid Sheet
Question Date: 1/21/2026 10:14:52 AM
Is the trench milling along curb and gutter going to be paid for as "removal up to 12" of material"?  
Answer   Date: 1/21/2026 3:01:47 PM
Trench milling along curb and gutter is incidental to appropriate bid items.  
 
Subject: Survey files Type: Plan
Question Date: 1/6/2026 7:42:14 AM
This is an advisory Q/A from the Department, to advise the bidders of publishing survey .dgn files to supplement the Proposal.  
Answer   Date: 1/6/2026 7:42:37 AM
The survey files are now published.  
 

Displaying questions 1 - 5 (of 5)