Question
|
|
Date:
|
9/17/2025 1:52:11 PM
|
|
Can the department please clarify the scope of work required for the expansion joint replacements? The proposal states that the contractor is responsible for chipping out abutment and pier joints, but the plans suggest simply removing the existing joint material, cleaning the deck concrete, and installing new joint sealer, which would not require chipping out the joint.
|
|
Answer
|
Date:
|
9/19/2025 9:43:51 AM
|
|
The Contractor is responsible for Expansion Joint Preparation; see VDOT Road and Bridge Specifications for procedures. For the existing steel plate/finger joints, the Contractor is required to replace all concrete material up to the joints within the thickness limits of the new overlay. See No-Plan Assembly under Scope of Work.
|
|
|
|
|
|
Question
|
|
Date:
|
9/17/2025 1:55:20 PM
|
|
Can the department please confirm the sealer size (b) at Pier 2 and 5 (NBL) and Pier 2 (SBL)? The table shows a 2" seal for a 2.25" opening.
|
|
Answer
|
Date:
|
9/19/2025 9:44:24 AM
|
|
The 2” seal is acceptable at those locations; it comes pre-compressed and will expand upon package removal. If the Contractor wishes to order a larger seal for these joints, they may do so at no additional cost to the Department.
|
|
|
|
|
|
Question
|
|
Date:
|
9/17/2025 11:40:35 AM
|
|
Can the department clarify the allowable work hours? The contract specifies 7pm-7am but the Bristol District Allowable Work Hours chart allows for more hours depending on the time of year. Is the contract requirement for all work or just the overlays?
|
|
Answer
|
Date:
|
9/19/2025 9:45:03 AM
|
|
Allowable work hours are for all work on this proposal.
|
|
|
|
|
|
Question
|
|
Date:
|
9/17/2025 10:47:48 AM
|
|
Is the intent of the HES Patching Type C bid item to perform full depth deck patching prior to deck milling or after deck milling for the latex overlay?
|
|
Answer
|
Date:
|
9/19/2025 9:45:46 AM
|
|
Intent is to do Type C Patching after deck milling; see Proposed Sequence of Construction within No-Plan Assembly.
|
|
|
|
|
|
Question
|
|
Date:
|
9/16/2025 5:17:30 PM
|
|
To what depth is the existing backwall to be removed?
|
|
Answer
|
Date:
|
9/19/2025 9:46:12 AM
|
|
Intent is to remove and replace any delaminated or unsound areas of backwall.
|
|
|
|
|
|
Question
|
|
Date:
|
9/16/2025 3:40:41 PM
|
|
Will the substructure concrete surface repairs be limited to the abutments and pier caps like the waterproofing, or should the contractor expect to sound and repair the full height of each pier? Access to the piers from below the bridge is extremely limited without clearing and grading, and the answer to this question will significantly impact the cost to access this repair work.
|
|
Answer
|
Date:
|
9/19/2025 9:46:42 AM
|
|
Limits of substructure concrete surface repair is limited to the abutments and pier caps; see Scope of Work within No-Plan Assembly.
|
|
|
|
|
|
Question
|
|
Date:
|
9/16/2025 1:03:01 PM
|
|
Please confirm if Bid item 412SD20-0003 is to be installed at what locations on substructure?
|
|
Answer
|
Date:
|
9/19/2025 10:36:59 AM
|
|
No bid item in proposal under this number.
|
|
|
|
|
|
Question
|
|
Date:
|
9/16/2025 1:01:16 PM
|
|
Please confirm if Bid item 412SD20-0003 is to be installed at what locations on superstructure?
|
|
Answer
|
Date:
|
9/19/2025 10:36:34 AM
|
|
No bid item in proposal under this number.
|
|
|
|
|
|
Question
|
|
Date:
|
9/16/2025 12:53:55 PM
|
|
Bid item 427SD20-0001 what are the locations? Joints at Approach?
|
|
Answer
|
Date:
|
9/19/2025 10:40:22 AM
|
|
See note 9 on sheet 207 of proposal. Location is between the abutment backwall and approach slabs.
|
|
|
|
|
|
Question
|
|
Date:
|
9/16/2025 1:01:16 PM
|
|
Please confirm if Bid item 412SD20-0003 is to be installed at what locations on superstructure?
|
|
Answer
|
Date:
|
9/19/2025 10:36:34 AM
|
|
No bid item in proposal under this number.
|
|
|
|
|
|
Question
|
|
Date:
|
9/16/2025 12:53:40 PM
|
|
Bid item 425SX20-0004 what are the locations? Complete bridge deck?
|
|
Answer
|
Date:
|
9/19/2025 10:46:15 AM
|
|
Yes, complete bridge deck.
|
|
|
|
|
|
Question
|
|
Date:
|
9/16/2025 1:01:16 PM
|
|
Please confirm if Bid item 412SD20-0003 is to be installed at what locations on superstructure?
|
|
Answer
|
Date:
|
9/19/2025 10:36:34 AM
|
|
No bid item in proposal under this number.
|
|
|
|
|
|
Question
|
|
Date:
|
9/16/2025 12:53:24 PM
|
|
Bid item 420SD20-0022 what are the locations? What is the final depth? Are we going below the rebar? Complete bridge deck?
|
|
Answer
|
Date:
|
9/19/2025 10:49:19 AM
|
|
No bid item in proposal under this number. See last note on sheet 206 of proposal.
|
|
|
|
|
|
Question
|
|
Date:
|
9/16/2025 1:01:16 PM
|
|
Please confirm if Bid item 412SD20-0003 is to be installed at what locations on superstructure?
|
|
Answer
|
Date:
|
9/19/2025 10:36:34 AM
|
|
No bid item in proposal under this number.
|
|
|
|
|
|
Question
|
|
Date:
|
9/16/2025 12:53:05 PM
|
|
Bid item 420SD20-0015 what are the locations? Complete bridge deck?
|
|
Answer
|
Date:
|
9/19/2025 10:50:52 AM
|
|
No bid item in proposal under this number.
|
|
|
|
|
|
Question
|
|
Date:
|
9/16/2025 1:01:16 PM
|
|
Please confirm if Bid item 412SD20-0003 is to be installed at what locations on superstructure?
|
|
Answer
|
Date:
|
9/19/2025 10:36:34 AM
|
|
No bid item in proposal under this number.
|
|
|
|
|
|
Question
|
|
Date:
|
9/16/2025 12:52:45 PM
|
|
Bid item 420SD20-0005 what are the locations? Complete bridge deck?
|
|
Answer
|
Date:
|
9/19/2025 10:51:58 AM
|
|
No bid item in proposal under this number.
|
|
|
|
|
|
Question
|
|
Date:
|
9/16/2025 1:01:16 PM
|
|
Please confirm if Bid item 412SD20-0003 is to be installed at what locations on superstructure?
|
|
Answer
|
Date:
|
9/19/2025 10:36:34 AM
|
|
No bid item in proposal under this number.
|
|
|
|
|
|
Question
|
|
Date:
|
9/16/2025 12:52:29 PM
|
|
Bid item 420SD20-0029 what are the locations? For expansion joints?
|
|
Answer
|
Date:
|
9/19/2025 10:53:33 AM
|
|
See sheet 210 of proposal for locations.
|
|
|
|
|
|
Question
|
|
Date:
|
9/16/2025 1:01:16 PM
|
|
Please confirm if Bid item 412SD20-0003 is to be installed at what locations on superstructure?
|
|
Answer
|
Date:
|
9/19/2025 10:36:34 AM
|
|
No bid item in proposal under this number.
|
|
|
|
|
|
Question
|
|
Date:
|
9/16/2025 12:52:11 PM
|
|
Bid item 412SD20-0049 what are the locations?
|
|
Answer
|
Date:
|
9/19/2025 10:54:22 AM
|
|
Locations to be determined from inspection reports by engineer during construction.
|
|
|
|
|
|
Question
|
|
Date:
|
9/16/2025 1:01:16 PM
|
|
Please confirm if Bid item 412SD20-0003 is to be installed at what locations on superstructure?
|
|
Answer
|
Date:
|
9/19/2025 10:36:34 AM
|
|
No bid item in proposal under this number.
|
|
|
|
|
|
Question
|
|
Date:
|
9/16/2025 12:51:54 PM
|
|
Bid item 412SD20-0046 what are the locations? Assuming at backwall
|
|
Answer
|
Date:
|
9/19/2025 10:55:11 AM
|
|
Yes.
|
|
|
|
|
|
Question
|
|
Date:
|
9/16/2025 1:01:16 PM
|
|
Please confirm if Bid item 412SD20-0003 is to be installed at what locations on superstructure?
|
|
Answer
|
Date:
|
9/19/2025 10:36:34 AM
|
|
No bid item in proposal under this number.
|
|
|
|
|
|
Question
|
|
Date:
|
9/16/2025 12:51:17 PM
|
|
Bid item 412SD20-0044 what are the locations? Assuming cutting the bridge deck transversely
|
|
Answer
|
Date:
|
9/19/2025 10:56:41 AM
|
|
Yes. Saw cutting is to be located at the armored joint locations. See note 6 on sheet 207 of proposal.
|
|
|
|
|
|
Question
|
|
Date:
|
9/16/2025 1:01:16 PM
|
|
Please confirm if Bid item 412SD20-0003 is to be installed at what locations on superstructure?
|
|
Answer
|
Date:
|
9/19/2025 10:36:34 AM
|
|
No bid item in proposal under this number.
|
|
|
|
|
|
Question
|
|
Date:
|
9/16/2025 12:50:49 PM
|
|
Bid item 412SD20-0043 what is the length of 1 joint? Assuming 29' from plans.
|
|
Answer
|
Date:
|
9/19/2025 10:57:39 AM
|
|
Quantity based off out to out of deck dimensions. Out to Out is 35’-2”. Quantity was rounded up.
|
|
|
|
|
|
Question
|
|
Date:
|
9/16/2025 1:01:16 PM
|
|
Please confirm if Bid item 412SD20-0003 is to be installed at what locations on superstructure?
|
|
Answer
|
Date:
|
9/19/2025 10:36:34 AM
|
|
No bid item in proposal under this number.
|
|
|
|
|
|
Question
|
|
Date:
|
9/16/2025 12:50:20 PM
|
|
Please confirm if Bid item 412SD20-0036 is to be installed at what locations? Is this amount fixed or is just a ROM and we find out at the time of construction and performing hydro-demolition?
|
|
Answer
|
Date:
|
9/19/2025 10:58:30 AM
|
|
Locations to be determined from inspection reports by engineer during construction.
|
|
|
|
|
|
Question
|
|
Date:
|
9/16/2025 1:01:16 PM
|
|
Please confirm if Bid item 412SD20-0003 is to be installed at what locations on superstructure?
|
|
Answer
|
Date:
|
9/19/2025 10:36:34 AM
|
|
No bid item in proposal under this number.
|
|
|
|
|
|
Question
|
|
Date:
|
9/16/2025 12:49:59 PM
|
|
Please confirm if Bid item 412SD20-0017 is to be installed on the entire bridge deck? What are the spacing requirements?
|
|
Answer
|
Date:
|
9/19/2025 10:59:46 AM
|
|
Anodes only installed in patched areas.
|
|
|
|
|
|
Question
|
|
Date:
|
9/16/2025 1:01:16 PM
|
|
Please confirm if Bid item 412SD20-0003 is to be installed at what locations on superstructure?
|
|
Answer
|
Date:
|
9/19/2025 10:36:34 AM
|
|
No bid item in proposal under this number.
|
|
|
|
|
|
Question
|
|
Date:
|
9/16/2025 12:49:41 PM
|
|
Please confirm if Bid item 412SD20-0020 is for entire bridge deck?
|
|
Answer
|
Date:
|
9/19/2025 11:01:15 AM
|
|
No bid item in proposal under this number.
|
|
|
|
|
|
Question
|
|
Date:
|
9/16/2025 1:01:16 PM
|
|
Please confirm if Bid item 412SD20-0003 is to be installed at what locations on superstructure?
|
|
Answer
|
Date:
|
9/19/2025 10:36:34 AM
|
|
No bid item in proposal under this number.
|
|
|
|
|
|
Question
|
|
Date:
|
9/16/2025 12:48:36 PM
|
|
Please confirm if Bid item 412SD20-0003 is to be installed at what locations?
|
|
Answer
|
Date:
|
9/19/2025 11:02:22 AM
|
|
No bid item in proposal under this number.
|
|
|
|
|
|
Question
|
|
Date:
|
9/16/2025 1:01:16 PM
|
|
Please confirm if Bid item 412SD20-0003 is to be installed at what locations on superstructure?
|
|
Answer
|
Date:
|
9/19/2025 10:36:34 AM
|
|
No bid item in proposal under this number.
|
|
|
|
|
|
Question
|
|
Date:
|
9/16/2025 12:47:34 PM
|
|
Please confirm if Bid item 412SD20-0061 is to be installed at what locations?
|
|
Answer
|
Date:
|
9/19/2025 11:03:19 AM
|
|
Locations to be determined from inspection reports by engineer.
|
|
|
|
|
|
Question
|
|
Date:
|
9/16/2025 1:01:16 PM
|
|
Please confirm if Bid item 412SD20-0003 is to be installed at what locations on superstructure?
|
|
Answer
|
Date:
|
9/19/2025 10:36:34 AM
|
|
No bid item in proposal under this number.
|
|
|
|
|
|
Question
|
|
Date:
|
9/16/2025 11:29:16 AM
|
|
Please confirm if Bid item 704SD20-0031 is for white solid line and white stripes
|
|
Answer
|
Date:
|
9/19/2025 10:14:13 AM
|
|
Item # 704SD20-0031 is the total quantity for Type B Class VI 6" black contrast pavement markings for the bridge.
|
|
|
|
|
|
Question
|
|
Date:
|
9/16/2025 1:01:16 PM
|
|
Please confirm if Bid item 412SD20-0003 is to be installed at what locations on superstructure?
|
|
Answer
|
Date:
|
9/19/2025 10:36:34 AM
|
|
No bid item in proposal under this number.
|
|
|
|
|
|
Question
|
|
Date:
|
9/16/2025 11:28:55 AM
|
|
Please confirm if Bid item 704SD20-0027 is for Yellow solid line
|
|
Answer
|
Date:
|
9/19/2025 10:15:17 AM
|
|
item # 704SD20-0027 is the Type B Class VI 6" pavement line markings total quantity (not color specific).
|
|
|
|
|
|
Question
|
|
Date:
|
9/16/2025 1:01:16 PM
|
|
Please confirm if Bid item 412SD20-0003 is to be installed at what locations on superstructure?
|
|
Answer
|
Date:
|
9/19/2025 10:36:34 AM
|
|
No bid item in proposal under this number.
|
|
|
|
|
|
Question
|
|
Date:
|
9/16/2025 12:41:24 PM
|
|
Please confirm if Bid item 412SD20-0055 is to be installed at what locations? What are the spacing requirements?
|
|
Answer
|
Date:
|
9/19/2025 11:04:34 AM
|
|
Anodes to be placed in patched areas determined by the engineer. Spacing requirements are per manufacturers’ recommendation.
|
|
|
|
|
|
Question
|
|
Date:
|
9/16/2025 11:28:14 AM
|
|
Please confirm if Bid item 515SD20-0004 is for approach area
|
|
Answer
|
Date:
|
9/19/2025 10:29:01 AM
|
|
Yes. Second note on sheet 207 of proposal states: Approach pavement (travel lanes and shoulders) shall be milled 100’on each end of bridge and paved to provide a smooth transition.
|
|
|
|
|
|
Question
|
|
Date:
|
9/16/2025 11:27:49 AM
|
|
Please confirm if Bid item 315SD20-0015 is for approach area
|
|
Answer
|
Date:
|
9/19/2025 10:29:43 AM
|
|
Yes.
|
|
|
|
|
|
Question
|
|
Date:
|
9/16/2025 11:27:16 AM
|
|
Please confirm if Bid item 315SD20-0003 is for entire bridge deck?
|
|
Answer
|
Date:
|
9/19/2025 10:30:27 AM
|
|
No. Asphalt Concrete TY. SM-12.5E is to only be used for approaches. Bridge deck and approach slabs shall not to be paved over.
|
|
|
|
|