Advertisements
Division Home
Bid Results
Bid Tabs
Ad Report
VDOT Forms
Login Or Create Account
Project Info
Order Number
UPC
State Project Number
Last Date to Post Questions
N08
115407
0600-026-656,C501
9/19/2025
Search Questions
Search
Question Type
All
Plan
Proposal
Bid Sheet
Permits
Specifications
Other
The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered.
Export Q&A
Question List
Subject:
Utiltiies
Type:
Proposal
Question
Date:
9/17/2025 3:23:04 PM
Will asphalt patching be incidental to the water and sewer relocation scope of work? or paid for at contract price per ton?
Answer
Date:
9/17/2025 8:44:41 PM
Any asphalt patching due to the proposed work of water and sewer should be incidental to the cost of water and sewer relocation.
Subject:
Waterline
Type:
Plan
Question
Date:
9/16/2025 10:34:20 AM
Can the engineer confirm the contractor will be required to restrain joints 60' back off connection points on the existing line? Is there a detail or requirement that can be posted regarding restraining existing A/C joints?
Answer
Date:
9/16/2025 3:34:32 PM
Joint restraint is required on the existing AC pipe for the insertion valve at Sta. 9+96 on Profile W-1. The plans specify to use a thrust anchor at this location per Thrust Anchor for AC Pipe Detail on sheet 7(7). All AC pipe joints between the furthest away JCM #630 restrainer installed with the thrust anchor (Sta. 9+96) and the AC to DIP coupling (Sta. 10+12) shall be restrained with additional JCM #630 restrainers.
Subject:
Undercut
Type:
Plan
Question
Date:
9/10/2025 3:28:17 PM
Will the #57s that will be required for the undercut per detail sheet 2a(3) be paid for under item 260 NS BEDDING NO 57? Or is that item intended for additional storm sewer PB-1 bedding only?
Answer
Date:
9/11/2025 9:56:51 AM
The #57s that will be required for the undercut per detail sheet 2A(3) and the additional storm sewer PB-1 bedding shall be paid for under item 260 NS BEDDING NO 57.
Subject:
ELECTRICAL SERVICE GROUNDING ELECTRODE
Type:
Bid Sheet
Question
Date:
9/10/2025 2:30:02 PM
It appears that an item for ELECTRICAL SERVICE GROUNDING ELECTRODE is missing
Answer
Date:
9/12/2025 7:49:11 AM
ELECTRICAL SERVICE GROUNDING ELECTRODE Is not needed at this time for the SE-5 as it will not be energized as part of this contract.
Subject:
Drainage
Type:
Proposal
Question
Date:
9/10/2025 9:52:54 AM
Per Geotech and plans there seem to be a lot of poor soils on this project. Can the department confirm pipe spoils and import for suitable backfill are to be included in the cost per linear foot for pipe and structures?
Answer
Date:
9/10/2025 2:29:47 PM
Unless otherwise noted in the drainage description for each structure and pipe, pipe spoils and import for suitable backfill are to be included in the cost per linear foot for pipes and included in the cost of each structure.
Subject:
Landscape Lighting - Electrical Service
Type:
Plan
Question
Date:
9/3/2025 5:02:35 PM
Will VDOT - Richmond District - Traffic Engineering be responsible for completing the Electrical Service Work Request with Dominion Energy for the electrical service, SE-5? If not, who will be responsible?
Answer
3 previous answer(s)
Date:
9/9/2025 2:45:18 PM
The SE-5 should be installed per the plans, but not energized.
Subject:
Merged Plan Set
Type:
Plan
Question
Date:
8/29/2025 10:26:48 AM
I see that someone requested the Merged plan set near 2 weeks ago. Is there an ETA on getting that file uploaded?
Answer
Date:
8/29/2025 11:30:30 AM
Sorry, merged plan set is now available.
Subject:
Proposal
Type:
Plan
Question
Date:
8/13/2025 11:15:20 AM
Will a combined set of plans be provided on ProjectWise? At the moment it is only showing individual pages.
Answer
Date:
8/13/2025 1:41:05 PM
Merged plan set is forthcoming.
Displaying questions 1 - 8 (of 8)
Page:
1
First
Previous
Next
Last
Construction Advertisement Bulletin Board (CABB)
Update Profile
CABB v2.0
© 2008 Virginia Department of Transportation
9/15/2026 1:26:19 AM
2008