Advertisements
Division Home
Bid Results
Bid Tabs
Ad Report
VDOT Forms
Login Or Create Account
Project Info
Order Number
UPC
State Project Number
Last Date to Post Questions
N01
111406
0001-089-738, B618, C501
9/19/2025
Search Questions
Search
Question Type
All
Plan
Proposal
Bid Sheet
Permits
Specifications
Other
The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered.
Export Q&A
Question List
Subject:
Cofferdams
Type:
Plan
Question
Date:
9/15/2025 10:37:45 AM
The plans indicate multiple cofferdams, but no schematics or detailed drawings have been provided. Please provide the relevant details or plan schematics for review.
Answer
Date:
9/16/2025 7:59:16 AM
The contract documents include permit sketches showing potential cofferdam locations. The final design, locations, and materials are the contractor’s means and methods, provided they stay within permitted limits and keep construction activities in dry conditions.
Subject:
Pier Demolition
Type:
Plan
Question
Date:
9/15/2025 10:31:34 AM
Would it be acceptable to cut the existing pier 3 feet below the surface, or does it need to be completely removed? Cutting it would help minimize environmental impact on the creek.
Answer
Date:
9/15/2025 10:40:55 AM
Please bid the plans and contract as advertised.
Subject:
Overhead Utilities
Type:
Plan
Question
Date:
9/15/2025 9:58:54 AM
Does VDOT Plan to have the overhead utility lines insulated during the demolition and construction of the proposed new bridge?
Answer
Date:
9/16/2025 1:15:30 PM
The overhead lines will not be insulated. The contractor must provide Dominion Transmission with at least 5 days’ notice before working near the lines and is fully responsible for implementing all necessary safety measures and obtaining the required insurance coverage.
Subject:
Lime
Type:
Bid Sheet
Question
Date:
9/12/2025 10:54:12 AM
Please advise if Bid Item 180: LIME is utilized for seeding or for stabilizing roadbed material? It is listed under the Roadside Development Summary on Sheet 2K but the Item ID refers to lime stabilization for roadway construction. If the lime is utilized for stabilizing roadbed material, please identify on the plans where the lime is to be placed.
Answer
Date:
9/12/2025 2:08:31 PM
The agricultural lime is for seeding and not for roadway soil stabilization.
Subject:
Bid Submission
Type:
Other
Question
Date:
8/22/2025 4:29:41 PM
Please confirm if the bid will still be submitted via portal or if it needs to be hand delivered.
Answer
Date:
8/25/2025 8:53:00 AM
Receipt of bids for this project has been delayed.
Subject:
Overhead Power Lines
Type:
Plan
Question
Date:
8/21/2025 1:39:28 PM
Please advise if the numbers along the overhead power lines on Sheet 7(4) are the elevations or the height differential from proposed grade.
Answer
Date:
8/28/2025 8:27:18 AM
The numbers shown along the overhead power lines on Sheet 7(4) represent elevations.
Subject:
Re-Paving
Type:
Other
Question
Date:
8/21/2025 8:37:50 AM
The current center line of the road has rumble strips, but in the plans does not show re-paving this section, nor the traffic control for that. Will this be addressed via change order? Or shall be considered incidental?
Answer
Date:
8/21/2025 3:08:46 PM
This item will be addressed as a change order. The length of the rumble strips is 1,550 LF.
Subject:
Incentives
Type:
Other
Question
Date:
8/21/2025 8:37:02 AM
Are there any incentives for early completion of the project?
Answer
Date:
8/21/2025 3:09:15 PM
Early completion incentives are not included in this project. To ensure timely delivery, the contractor is required to maintain an approved progress schedule in accordance with Special Provision SP108-000110-01, as outlined in the proposal.
Subject:
Special Provisions
Type:
Other
Question
Date:
8/21/2025 8:36:40 AM
Can you please provide the special provision for item 450, 460 and 520?
Answer
Date:
8/21/2025 3:10:13 PM
Items 450 and 460 are covered under VDOT Road and Bridge Specification Section 413, and item 520 is covered under Section 430. No special provisions apply to these items, as the standard specifications are sufficient. Please refer to the current VDOT R&B Specification Book for full details. The applicable bridge structure No. is 1016.
Subject:
Line Item 450
Type:
Other
Question
Date:
8/21/2025 8:36:06 AM
Because of the phasing of the project, can you please indicate how line item 450 will be paid?
Answer
Date:
8/21/2025 3:10:45 PM
Payment for line item 450, “Dismantle and remove existing structure”, will be made at the contract lump sum price, as stated in Section 413 of the VDOT Road and Bridge Specifications. The applicable bridge structure is Structure No. 1016.
Displaying questions 1 - 10 (of 24)
Page:
1
2
3
First
Previous
Next
Last
Construction Advertisement Bulletin Board (CABB)
Update Profile
CABB v2.0
© 2008 Virginia Department of Transportation
12/11/2025 8:03:20 PM
2008