Project Info
Order Number
UPC
State Project Number
Last Date to Post Questions
L11 w/d
5559
0638-029-156, C504
7/19/2024
Search Questions
Search
Question Type
All
Plan
Proposal
Bid Sheet
Permits
Specifications
Other
The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered.
Export Q&A
Question List
Subject:
Subbase - CTA Special Provision
Type:
Specifications
Question
Date:
7/18/2024 3:54:40 PM
On the typical section sheets 2A(1) through 2A(10); call out #4 for Subbase - 6" Cement Treated Aggregate (CTA) and call out #19 - 8" Cement Treated Aggregate (CTA) indicate that they should be in accordance with Special Provision for CTA dated June 18,2020. Please provide the Special Provision, we could not locate it in the bid documents or plans or on the VDOT website.
Answer
Date:
Subject:
Valve Box Alignment Device
Type:
Specifications
Question
Date:
7/17/2024 4:12:47 PM
Please include the BOXLOK as a requirement for ALL buried valves, new and existing (for reset due to shift) and accessed from the surface via a conventional cast iron valve box or 6" PVC pipe to eliminate VBS - Valve Box Shift and assure proper operation. PDF submittal details available upon request. Please view this short YouTube video for further explanation. My email and phone, as I understand, are part of my CABB registration for additional information or questions. https://youtu.be/ioEGZ47HIiM?si=GCH9hEmS0Acz12Zk
Answer
Date:
Subject:
Manipulation and Hydraulic Cement
Type:
Bid Sheet
Question
Date:
7/17/2024 3:43:04 PM
Bid item #0700 is listed as 10 tons of Hydraulic Cement. This does not account for a 12" mixing depth with 12% cement by volume. Will the bid item for Hydraulic Cement (0700) be updated to accurately reflect the application rate?
Answer
Date:
Subject:
MSE Walls
Type:
Specifications
Question
Date:
7/17/2024 3:34:04 PM
Please provide further information in regards to the size and pattern of the panels to be used in the MSE Walls.
Answer
Date:
Subject:
Sound Barrier Wall
Type:
Specifications
Question
Date:
7/17/2024 9:44:00 AM
Section 519 specifies that “The sound barrier will be measured in square feet of surface area from the finished grade to the sound attenuation line shown on the plans.” The proposed front of wall grade is higher than the proposed grade on the back of the wall in some instances and some instances it is the opposite. Please confirm which proposed grade will be used to determine the bid item quantity or if it will be the higher elevation of the two proposed grades.
Answer
Date:
Subject:
Temp Pavement for Phase 1 Drainage Crossings
Type:
Plan
Question
Date:
7/17/2024 8:28:14 AM
Regarding the addendum that addressed the storm sewer drainage sequence: Will the department please add temporary pavement at each of the crossings that require flagging to get across Rolling Road during the Phase 1 MOT sequence of construction? The existing pavement width does not appear to be adequate to maintain one lane of traffic in each direction and install full sticks of pipe across the road.
Answer
Date:
Subject:
MSE Wall Panel Size
Type:
Specifications
Question
Date:
7/16/2024 5:41:57 PM
Should the precast concrete panels for the mse wall be 5'x5' or 5x10"?
Answer
Date:
Subject:
Cross Sections
Type:
Plan
Question
Date:
7/16/2024 3:17:08 PM
Per cross section sheet X-66, there is a DEV pole in conflict with Sound Barrier Wall G at Sta 2050+35, please indicate how to proceed.
Answer
Date:
7/18/2024 9:57:11 AM
The Dominion pole shown on cross sections at Sta 2050+35 has subsequently been relocated to the northbound side of Rolling Road and will not be in conflict with Sound Barrer Wall G.
Question
Date:
7/16/2024 3:16:10 PM
Per Cross section sheet, there is a pole at station 2012+76 that will be affected by the excavation. Will this pole be relocated by Dominion Energy prior to construction? If not, please indicate how to proceed.
Answer
Date:
7/18/2024 10:04:34 AM
The 4’ cut to finish grade was considered when Dominion Pole #PL77 was set, this pole was set at a depth of 12’ and will have approximately 8’ in the ground after the excavation is completed.
Subject:
Clarfication
Type:
Other
Question
Date:
7/12/2024 3:56:01 PM
Please clarify if the quantity of concrete for the Moment Slab in Retaining Wall 1 is considered as part of the 177 CY?
Answer
Date:
7/15/2024 5:50:14 PM
Quantity of concrete for Moment Slab is not part of the 177 CY. The 177 CY is the concrete quantity for Retaining Wall RW-3. Concrete for Moment Slab shall be in accordance with Special Provision PRECAST MOMENT SLABS.
Subject:
Type:
Bid Sheet
Question
Date:
7/12/2024 3:55:02 PM
Please confirm item 1370 corresponds to the demolitions listed in sheet 2E(8), and that all of those structures are to be demolished and not relocated.
Answer
Date:
7/15/2024 5:20:27 PM
Item 1370 DEMO. OF BLDG.DEMOLITION OF STRUCTURES corresponds to the demolitions listed on sheet 2E(8). Items on Sheet 2E(8) are to be demolished and not relocated.
Displaying questions 1 - 10 (of 32)
Page:
1
2
3
4
First
Previous
Next
Last
Construction Advertisement Bulletin Board (CABB)
Update Profile
CABB v2.0
© 2008 Virginia Department of Transportation
3/21/2025 6:14:49 AM
2008