Project Info
Order Number UPC State Project Number Last Date to Post Questions
L21 121246 0077-010-752, B645, B646 5/17/2024
Search Questions
Search
Question Type  
    The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered. Export Q&A    
Question List
Subject: Roadway plans Type: Plan
Question Date: 5/14/2024 4:19:32 PM
Will VDOT be posting Roadway plans?  
Answer   Date: 5/15/2024 7:12:28 AM
Plans have been posted.  
 
Subject: MOT Type: Plan
Question Date: 5/14/2024 1:00:26 PM
The Mot Closure Schedule Table is hard to read. Please upload a document more legible. Thank you.  
Answer   Date: 5/14/2024 1:35:04 PM
Sheet 6 of proposal shows amended limits of operations table.  
 
Question Date: 5/17/2024 7:50:14 AM
How would payment be issued for a temporary signal if it were proposed and found to be acceptable to the Department for the project?  
Answer   Date: 5/20/2024 10:38:17 AM
No payment would be made for a temporary signal if allowed for use.  
 
Question Date: 5/14/2024 12:58:37 PM
Would VDOT allow a continuous MOT operation on Route 52 utilizing a temporary traffic control signal?  
Answer   Date: 5/14/2024 1:41:39 PM
Department would consider it if it makes sense in the context of the project and if can be done in accordance with our standards.  
 
Question Date: 5/17/2024 7:50:14 AM
How would payment be issued for a temporary signal if it were proposed and found to be acceptable to the Department for the project?  
Answer   Date: 5/20/2024 10:38:17 AM
No payment would be made for a temporary signal if allowed for use.  
 
Question Date: 5/17/2024 7:50:14 AM
How would payment be issued for a temporary signal if it were proposed and found to be acceptable to the Department for the project?  
Answer   Date: 5/20/2024 10:38:17 AM
No payment would be made for a temporary signal if allowed for use.  
 
Subject: MOT Type: Bid Sheet
Question Date: 5/14/2024 1:41:42 PM
Please disregard the above question.  
Answer   Date:
 
 
Question Date: 5/14/2024 1:41:42 PM
Please disregard the above question.  
Answer   Date:
 
 
Question Date: 5/14/2024 12:53:51 PM
Based on the Bid documents, this project is to be done utilizing nightly closures for Hydro-Demo. The hours are 7 PM - 6AM. Based on this information, each hydro section will be turnkey to give traffic back and poured with an 11 hour timeframe. This is very difficult. Would the Department entertain a continuous lane closure through the week or weekend?  
Answer   Date: 5/14/2024 1:33:16 PM
Special Provision Limits of Operations on sheet 6 of proposal states the following: Allowable Work Hours for Single Lane Closures for Labor Day through Memorial Day shall allow the Contractor 24-hour lane closures starting on Sundays at 7PM and ending on Thursdays by 7AM.  
 
Question Date: 5/14/2024 1:41:42 PM
Please disregard the above question.  
Answer   Date:
 
 
Subject: Beam Ends Type: Plan
Question Date: 4/29/2024 1:47:39 PM
Does the DOT intend for the bridge to be jacked during beam end operations? If so, is that price to be included in the beam end item?  
Answer   Date: 4/29/2024 2:01:01 PM
Note on sheet 3 of 6 in plan set states, “Beams shall not be jacked; all deteriorated concrete on beam end bottoms directly above bearings shall remain.”  
 

Displaying questions 1 - 4 (of 4)