Project Info
Order Number
UPC
State Project Number
Last Date to Post Questions
K84
111391
0003-057-593, B607
4/19/2024
Search Questions
Search
Question Type
All
Plan
Proposal
Bid Sheet
Permits
Specifications
Other
The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered.
Export Q&A
Question List
Subject:
Diaphragms
Type:
Plan
Question
Date:
4/19/2024 3:12:38 PM
Bridge Plans Sheet 10 calls out the intermediate diaphragms. Sheet 11 mentions end diaphragms. Please confirm there are no steel channel end diaphragms on this bridge, only closure diaphragm concrete.
Answer
Date:
4/22/2024 9:47:15 AM
There are no steel channel end diaphragms.
Subject:
Parapet
Type:
Plan
Question
Date:
4/19/2024 3:10:39 PM
Bridge Plans Sheet 20 and 23 have conflicting limits of payment for the railing. Sheet 20 shows that terminal walls are not included within the railing item, 23 shows the opposite. Please confirm the measurement limits for the parapet and terminal wall.
Answer
Date:
4/22/2024 10:14:13 AM
Bridge Plan Sheets 20 and 23 are VDOT Standard CPSR-1 CPSRT-3 Details. And the limits indicate the limit on the superstructure, however both 42” CPSR Railing and 42” CPSR Terminal Wall are accounted in the quantity item for Railing, CPSR 2 rail in Bridge Plan Sheet 2 of 27.
Question
Date:
4/19/2024 3:11:29 PM
Sheet 20 has two section details of the railing, one of which shows a sidewalk. Sheet 9 showing the transverse section of bridge deck does not show a sidewalk. Please confirm there is no sidewalk to be constructed on this bridge.
Answer
Date:
4/22/2024 10:14:39 AM
Bridge Plan Sheets 20 is a VDOT Standard CPSR-1 Detail. It includes the details for the cases with and without sidewalk. However, the details with the sidewalk do not apply to this project.
Subject:
HAZMAT
Type:
Specifications
Question
Date:
4/5/2024 12:41:36 PM
HAS AN ASBESTOS OR HAZARDOUS MATERIAL REPORT BEEN COMPLETE FOR THE EXISTING BRIDGE? AND IF SO, CAN IT BE PROVIDED?
Answer
Date:
4/15/2024 2:45:24 PM
Two (2) reports are now available: HAZMAT Summary Report; and, Potential Asbestos Containing Materials Checklist.
Subject:
AS-BUILTS
Type:
Plan
Question
Date:
4/5/2024 12:40:35 PM
CAN THE AS-BUILT DRAWINGS FOR THE EXISTING BRIDGE BE PROVIDED?
Answer
Date:
4/8/2024 10:57:57 AM
The as builts are now available for the contractors to view.
Subject:
Elastic Inclusion
Type:
Proposal
Question
Date:
3/28/2024 10:51:11 AM
I cannot find the Special Provision for Elastic Inclusion in the current proposal. Can the department please add this provision to the proposal? Thanks!
Answer
Date:
3/28/2024 11:45:44 AM
Please see page 5 of proposal.
Question
Date:
4/2/2024 10:18:13 AM
Looking for the 3 page material specification provision for Elastic Inclusion.
Answer
Date:
4/2/2024 11:06:49 AM
This will be added via forthcoming addendum.
Displaying questions 1 - 5 (of 5)
Page:
1
First
Previous
Next
Last