Advertisements
Division Home
Bid Results
Bid Tabs
Ad Report
VDOT Forms
Login Or Create Account
Project Info
Order Number
UPC
State Project Number
Last Date to Post Questions
L01
115480
0089-038-791,C501
3/22/2024
Search Questions
Search
Question Type
All
Plan
Proposal
Bid Sheet
Permits
Specifications
Other
The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered.
Export Q&A
Question List
Subject:
24" Bored & Jacked Pipe
Type:
Plan
Question
Date:
3/13/2024 9:28:23 AM
PerSheet 9(4) the 24" pipe from 4-2 to 4-13 is shown to be a bored & jacked RCP. 1. can this B&J pipe be Welded Steel Pipe in-lieu of concrete? 2. Per sheet 8 the pipe from 4-2 to 4-13 is shown to receive a cradle as well. How can the pipe be both bored and jacked and have a CIP cradle?
Answer
Date:
3/13/2024 1:49:04 PM
The pipe needs to be concrete, with the intent of providing a concrete cradle under the upstream portion that can be installed by open cut, then continuing without for the jack & bore portion.
Displaying questions 1 - 1 (of 1)
Page:
1
First
Previous
Next
Last
Construction Advertisement Bulletin Board (CABB)
Update Profile
CABB v2.0
© 2008 Virginia Department of Transportation
4/17/2025 10:16:26 AM
2008