Subject: Project Time Type: Proposal
Question Date: 3/21/2024 6:48:57 AM
Will the 180 day contract time limit start being charged to do just the exploratory work for the new signals?  
Answer   Date: 3/21/2024 11:27:23 AM
There is an SPCN within the bid proposal titled "Prosecution of Work." It says "The Contractor may schedule and perform work on this Contract any time within the fixed time limit set forth in the Contract; however, once Contract work commences, the Contractor shall complete all Contract work, including burn-in period, within 180 calendar days." Given that the fixed time limit is 180 days and the Contract Completion Date is 9/4/2025, any exploratory work (that doesn't involve MOT) done for the new signals prior to the beginning of the fixed time limit would not equate to days expended within the 180 day allotment.  
 
Question Date: 3/22/2024 11:34:59 AM
Due to the speed limit at 55 MOT will be required to do signal test bores. Will the department be willing to open the project to do test bores only and reopen once actual construction begins?  
Answer   Date: 3/26/2024 8:24:15 AM
The contractor will be expected to continuously prosecute work once the notice to proceed is requested and approved. However, upon receipt of the letter notifying of the executed contract, the Contractor may perform test bores and required MOT prior to the selected NTP. The 180 days will begin at the contractor’s requested NTP date.  
 
Subject: Length of contract Type: Proposal
Question Date: 3/12/2024 10:49:20 AM
What is the length of this contract? I see metal poles and they have a 180 day lead time.  
Answer   Date: 3/12/2024 10:58:31 AM
The Time Limit for this contract - as identified in the proposal as well as on CABB - is 9/04/2025.  
 

Displaying questions 1 - 2 (of 2)