Subject: Construction Completion Date Type: Proposal
Question Date: 2/15/2024 2:55:41 PM
The Construction Completion Date in the C-7 of the proposal shows 11/01/24 but the Time Limit on CABB shows 11/15/24. Which is correct?  
Answer   Date: 2/15/2024 2:57:19 PM
The Construction Completion Date is 11/01/24. The Time Limit on CABB has been corrected.  
 