Subject: Patching Type: Specifications
Question Date: 2/6/2024 3:51:37 PM
According to the proposal, the BM-25.0D used for patching is only allowed to be subject to traffic for 14 days. Would it be acceptable to use IM-19.0D in lieu of BM-25.0D for the purposes of allowing the patches to be subject to traffic for a longer period of time?  
Answer   Date: 2/8/2024 8:45:26 AM
The Department will consider replacing the Base Mix (BM-25.0D) used for deep patching with Intermediate Mix (IM-19.0D) at the Construction phase with no additional cost to the Department.  
 
Subject: Completion Date Type: Proposal
Question Date: 2/5/2024 2:33:49 PM
According to the proposal, it states that the completion date for this schedule is November 15, 2024. Would VDOT consider extending the completion date to June 30, 2025?  
Answer   Date: 2/5/2024 3:22:53 PM
The Completion date will remain unchanged.  
 