Project Info
Order Number UPC State Project Number Last Date to Post Questions
K32 111648 7017-156-308, C501 2/23/2024
Search Questions
Search
Question Type  
    The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered. Export Q&A    
Question List
Subject: WAGE RATES for WRONG COUNTY Type: Other
Question Date: 2/26/2024 12:29:15 PM
It was just brought to my attention that the wage rates provided " Programmatic Addendum Letter_20240112_Signed" are for Arlington County and City of Alexandria. They seem extraordinarily high. Please confirm if this is the intended rates or it is a mistake?  
Answer   Date:
 
 
Question Date: 2/26/2024 12:40:29 PM
Disregard, I see that the rates provided were for all Counties and Cities in VA. I was able to locate Fauquier's rates within.  
Answer   Date:
 
 
Subject: Lane Closure House Type: Plan
Question Date: 2/25/2024 3:16:52 PM
TMP plans indicate that all lane closures must be at night. Lane closures are required daily for construction of this project. Does VDOT really expects the contractor to construct the entire project at night? This will be logistically very difficult and nearly impossible. Given the width of the roadway and the presence of two center turning lanes for nearly the entire length of the construction zone, day time construction won't affect the traffic much. Please consider allowing this project to be constructed during daytime hours.  
Answer   Date: 2/26/2024 8:37:56 AM
Notes on Sheet 01J(1) indicate lanes closures are permitted between 8:00pm and 6:00am. Lanes closures outside those hours may be submitted to VDOT on a case-by-case basis.  
 
Subject: Measurement and Payment Type: Bid Sheet
Question Date: 2/23/2024 12:40:45 PM
Please confirm the quantities provided for MS-2 were measured along the face of the curb per spec 502.04  
Answer   Date: 2/23/2024 2:23:04 PM
Quantities were established in accordance with standards and specifications.  
 
Subject: Historial Contaminated Soil Type: Other
Question Date: 2/23/2024 12:17:29 PM
Could you provide a historical contaminated soil sample.  
Answer   Date: 2/23/2024 2:22:44 PM
No mapping of contaminated soil is available.  
 
Subject: Water Service Connections Type: Plan
Question Date: 2/23/2024 12:15:11 PM
Are there any Water Service Connections to be performed in this project? None is shown in the drawings, but details were provided.  
Answer   Date: 2/23/2024 2:22:20 PM
Details shown for water meter/valve shown in Summary on Sheet 19(1).  
 
Subject: Borrow Backfill Type: Other
Question Date: 2/23/2024 12:14:07 PM
Is the borrow backfill incidental to the disposal of contaminated soil?  
Answer   Date: 2/23/2024 2:21:34 PM
Procedures and Measure & Payment are covered in the special provision.  
 
Question Date: 2/23/2024 12:13:30 PM
Does the borrow backfill to replace the contaminated material contemplated on this item?  
Answer   Date: 2/23/2024 2:47:40 PM
Borrow excavation pay item covers materials not covered under containment soils procedures and measure & payment.  
 
Subject: LUP Permit Type: Permits
Question Date: 2/23/2024 12:12:11 PM
Is an LUP Permit required? If so, can you provide a budget cost for the LUP Estimate so we may factor in the bond cost?  
Answer   Date: 2/23/2024 2:20:33 PM
No additional permits are needed unless specified in the contract and/or plans.  
 
Subject: Existing Utilities Type: Other
Question Date: 2/23/2024 12:10:52 PM
Can you provide a website or documentation showing actual existing utilities?  
Answer   Date: 2/23/2024 2:20:12 PM
Existing utilities are shown in the plans.  
 
Question Date: 2/23/2024 12:08:23 PM
Will the owner reimburse for existing utilities damaged if not shown on the plans?  
Answer   Date: 2/23/2024 2:18:47 PM
Contractor is responsible for MISS UTILITY requirements.  
 
Subject: Geotechnical Report Type: Other
Question Date: 2/23/2024 12:10:09 PM
When actual conditions are different from the geotechnical report/information provided, will the contractor be entitled for additional compensation?  
Answer   Date: 2/23/2024 2:19:39 PM
No.  
 
Subject: Notice to Proceed Type: Other
Question Date: 2/23/2024 12:09:14 PM
Due to current supply chain issues, will the owner consider issuing a second NTP for delays due to material availability?  
Answer   Date: 2/23/2024 2:19:16 PM
A single NTP is recommended.  
 

Displaying questions 1 - 10 (of 15)