Question List
Subject: Pipe Patch Type: Plan
Question Date: 1/9/2024 4:30:00 PM
Did VDOT do a CCTV inspection of the 48" CMP showing the 2 square cuts called out in the plans? What is the size and condition of the square cuts in the pipe? What type of patch/repair method will be acceptable?  
Answer   1 previous answer(s) Date: 1/10/2024 12:20:02 PM
A CCTV inspection was not performed. Re. Description of the cutouts: During the site visit, the inside of Pipe 003 was explored. A 2.1’ x 2.1’ square opening in the top of the pipe was encountered. The opening was covered by one band or an extra band. Downstream of the first square opening a second 1.1’ x 1.1’ cut in the top of the pipe was encountered. This cut was not covered by a band. It was covered by concrete rubble material.  
 
Subject: MOT Phase 4 and 5 International Parkway Type: Plan
Question Date: 1/5/2024 11:52:19 AM
Transportation Management Plan Phase 4 (Plan sheet 1J(30)) Note 2. States “Close RTE 220 New Left NB Turn Lane as shown on Sheet 1J(12) “ but signage is nor shown. Transportation Management Plane Phase 5 (plan sheet 1J(16 )) shows temporary signage on the northbound lane for no U-turn or left turn onto INT’L PKWY but no physical barrier restricting access is shown. Please confirm the median will be closed to left turns onto INT’L PKWY during Phase 4 and Phase 5  
Answer   1 previous answer(s) Date: 1/9/2024 3:24:33 PM
The Department will be issuing an addendum to allow for continual lane closures as part of Phases 1 and 2 of the TMP.  
 
Subject: MOT Phases 3,4,5 Ashley Way Type: Plan
Question Date: 1/5/2024 11:42:33 AM
Transportation Management Plane Phase 3 (plan sheet 1J(9)), Phase 4 ( plan sheet 1J(12)) and Phase 5 (Plan Sheet 1J(16)) have signage at approximate STA 220+25 for no left turn onto Ashley Way but no physical barrier restricting access to the turn lane is shown. Please confirm the median will be closed to left turns onto Ashley Way upon completion of the U turns in Phase 2.  
Answer   1 previous answer(s) Date: 1/9/2024 3:24:45 PM
The Department will be issuing an addendum to allow for continual lane closures as part of Phases 1 and 2 of the TMP.  
 
Subject: MOT Phase 2 RTE 220 SB Type: Plan
Question Date: 1/5/2024 11:41:28 AM
Transportation Management Plan (sheet 1J(2) requires the southbound lane to be opened from 6:00 A.M. until 9:00 A.M. M-F. The Typical Sections (sheets 2A(2) and 2A(3)) show a typical saw cut of 2’ into the travel lanes. The south bound inside lane will be under 10’ in width during Phase 2 construction and excavation depth adjacent to pavement will be over 2’. The contract does not include pay items for temporary pavement markings, temporary concrete barrier or signage of reduced lane widths. It is not possible to saw cut and remove the shoulder and two feet of the existing travel lane and safely maintain two travel lanes. South bound inside lane closure will need to be continuous through Phase 2 to perform this work. Please confirm the southbound lane closure shown in Phase 2 will be continuous or advise of what revisions will be made to the MOT plan.  
Answer   1 previous answer(s) Date: 1/9/2024 3:24:58 PM
The Department will be issuing an addendum to allow for continual lane closures as part of Phases 1 and 2 of the TMP.  
 
Subject: MOT Phase 2 RTE 220 NB Type: Plan
Question Date: 1/5/2024 11:39:36 AM
Transportation Management Plan (sheet 1J(2) requires the north bound lane to be open from 3:00 P.M. M-F. The Typical Sections (sheets 2A(2) and 2A(3)) show a typical saw cut of 2’ into the travel lanes. The north bound inside lane will be less than 9’ in width during Phase 2 construction and excavation depth adjacent to pavement will be over 2’. The contract does not include pay items for temporary pavement markings, temporary concrete barrier or signage of reduced lane widths. It is not possible to saw cut and remove the shoulder and two feet of the existing travel lane2’ pavement and safely maintain two travel lanes. North bound inside lane closure will need to be continuous through Phase 2 to perform this work. Please confirm the north bound lane closure shown in Phase 2 will be continuous or advise of what revisions will be made to the MOT plan.  
Answer   1 previous answer(s) Date: 1/9/2024 3:25:14 PM
The Department will be issuing an addendum to allow for continual lane closures as part of Phases 1 and 2 of the TMP.  
 
Subject: MOT Phase 1 RTE 220 N Type: Plan
Question Date: 1/5/2024 11:37:45 AM
Transportation Management Plan (sheet 1J(2) requires the north bound lane to be open from 3:00 P.M. until 5:00 P.M. M-F. The Typical Sections (sheets 2A(2) and 2 A(3)) show a typical saw cut of 2’ into the travel lanes The north bound outside lane will be less than 10’ in width during Phase 1 construction and excavation depth adjacent to pavement will be over 2’. The contract does not include pay items for temporary pavement markings, temporary concrete barrier or signage of reduced lane widths. I t is not possible to saw cut and remove the shoulder and 2’ of existing travel lane pavement and safely maintain two travel lanes. Lane closures will need to be continuous through Phase 1 to perform this work. Please confirm the north bound lane closure shown in Phase 1 will be continuous or advise of what revisions will be made to the MOT plan.  
Answer   Date: 1/9/2024 3:25:29 PM
The Department will be issuing an addendum to allow for continual lane closures as part of Phases 1 and 2 of the TMP.  
 
Subject: Storm Pipe Clarification Type: Plan
Question Date: 1/5/2024 8:44:05 AM
Str. 5-7 to 5-5 calls for 65' of 24" conc. storm sewer pipe in the drainage description. The bid items have this quantity included in the 24" Storm Sewer Pipe. Is this run of pipe required to be concrete pipe or is Storm Sewer Pipe (HDPE) acceptable?  
Answer   Date: 1/5/2024 12:59:33 PM
Storm Sewer Pipe (HDPE) is not acceptable. Only concrete pipe is acceptable.  
 
Subject: Geotechnical Report Type: Other
Question Date: 1/2/2024 3:23:56 PM
Could you post the project geotechnical report?  
Answer   Date: 1/4/2024 8:14:44 AM
The geotechnical report has now been posted.  
 