Question List
Subject: Spot Milling Type: Plan
Question Date: 11/22/2023 8:55:40 AM
Route 638 MP 0.0 to MP 0.78 Patrick County calls for 259 tons of Asph. Conc. BMD P+VO SM-9.5A Spot Patching at 1.5" depth but there is no Spot Milling quantity shown for that Route. Route 623 MP 3.52 to MP 5.10 Patrick County calls for 302 tons of Asph. Conc. BMD P+VO SM-9.5A Spot Patching at 1.5" depth but there is no Spot Milling quantity shown for that Route. Will Spot Milling quantities be added to each Route?  
Answer   Date: 11/27/2023 11:37:17 AM
“The 259 and 302 patching tonnages require no spot milling according to the pavement condition evaluation conducted by the Residency. The patching tonnages in question shall be placed on the pavement surface to fix the distressed areas that will be pointed out by the Residency. As stated in the contract, the Contractor shall contact the Residency at least 2 weeks prior to the start of paving operations so that the Residency may have sufficient time to mark the spot patching locations.  
 