Subject: sign mounting details for double indicated chevron locations Type: Specifications
Question Date: 9/20/2022 10:41:12 AM
Please clarify the following: What is the mounting height to the bottom of the chevron locations? Please provide sign mounting details for locations that are double indicated. The signs come with pre-punched holes in the center of each panel. This will not allow them to be properly aligned with traffic in both directions.  
Answer   1 previous answer(s) Date: 9/22/2022 2:15:53 PM
Given the rural nature of many of these curves, a 5-foot mounting height for chevrons is acceptable. In order to double-mount chevron posts to face each respective direction, it is recommended to pre-punch the holes on the side of the chevron sign panel instead of in the center. An example of such an application can be found at the following location: https://www.google.com/maps/@37.3356634,-77.4816428,3a,68.2y,353.06h,75.66t/data=!3m6!1e1!3m4!1sz4MR4znBj7uI5itVg6DL-w!2e0!7i16384!8i8192  
 
Subject: Plans or drawings for project Type: Proposal
Question Date: 9/16/2022 10:24:42 AM
The proposal does not provide any project information other than pay items and quantities. Are there any plan details or drawings?  
Answer   1 previous answer(s) Date: 9/16/2022 2:17:56 PM
Additional information is now available for viewing via Project Wise, located in the H81_115887 Site Locations.set file  
 

Displaying questions 1 - 2 (of 2)