Project Info
Order Number UPC State Project Number Last Date to Post Questions
H73 118977 0095-089-801, B670 9/23/2022
Search Questions
Search
Question Type  
    The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered. Export Q&A    
Question List
Subject: Maintenance of Traffic Type: Plan
Question Date: 9/22/2022 1:28:33 PM
Since the I-95 NB general purpose traffic is being shifted fully to the new bridge B609 for the duration of the rehabilitation, is the Contractor responsible for the set up and maintenance of the traffic for the detour and if so can details be provided?  
Answer   Date: 9/23/2022 1:11:59 PM
Maintenance of traffic is not required for this contract as there will be no traffic on the bridge during I-95 NB rehabilitation. Wagman contractor will take care of any traffic detour or changes, if necessary.  
 
Subject: Substructure Concrete Repairs Type: Plan
Question Date: 9/22/2022 8:58:49 AM
Please confirm that all of the substructure concrete repair work related to the piers is limited to the pier caps.  
Answer   Date: 9/23/2022 1:12:23 PM
Concrete substructure surface repair is limited to only the top face of the pier caps and edges per plan sheet 6 note 2.  
 
Subject: Elastomeric Pads Type: Other
Question Date: 9/22/2022 8:20:33 AM
When does VDOT expect to have the Elastomeric Pads ready for the contractor?  
Answer   Date: 9/23/2022 1:12:52 PM
VDOT will have the Elastomeric Pads at the area headquarters facility on or before April 14th, 2023.  
 
Subject: Anodes Type: Plan
Question Date: 9/21/2022 10:41:22 AM
Are anodes expected to be installed in the expansion joint reconstruction and deck joint closure items? If so, will they be considered incidental or will they be added to the anode item?  
Answer   Date: 9/23/2022 1:13:18 PM
Galvanic anode installation is not required as part of the expansion joint reconstruction or the deck slab closure rehabilitations.  
 
Subject: TIME Type: Plan
Question Date: 9/19/2022 2:08:57 PM
By the time the contractor gets the award and a precon, it will be late November 2022. 12 Months for this project is tight. Please consider adding more time to the contract as the review process for submittals and fabricating steel takes time, (as well as performing the work.)  
Answer   Date: 9/19/2022 4:37:43 PM
There will be no changes to the contract time.  
 
Subject: Concrete Surface Penetrant Sealer for Barriers Type: Plan
Question Date: 9/15/2022 12:35:14 PM
Plan Sheet 2 of 23 Note 8 of the Repair Work Above Deck section states this work is optional. Please clarify.  
Answer   Date: 9/19/2022 9:56:13 AM
All construction activities must be completed on the bridge in accordance with ‘Special Provision – Limitation of Operations’. During construction if it is determined that application of the concrete penetrant sealer to the barriers will extend past the limits of operation dates then this item may be removed from the project with written approval from VDOT.  
 
Question Date: 9/15/2022 12:34:40 PM
Please specify the limits of concrete surface penetrant sealer for the barriers.  
Answer   3 previous answer(s) Date: 9/27/2022 11:11:40 AM
Limits of surface penetrant sealer for concrete barriers include front face and top face only for full length of both bridge barriers extending to the end of terminal walls.  
 
Subject: REF: Bearing replacement details. Type: Plan
Question Date: 9/12/2022 1:47:14 PM
Need clarity. The dimensions referenced on the drawings do not agree with each other. As one example piers 1, 3, 5 & 7 the overall combined height is listed at 3.75" but the 4.66" bearing and 1.50" sole plate add up to 6.16" overall. The overall combined length of the sole plate is listed at 36" but the 24" anchor centers and 3" edge distance for the hole add up to 30" overall. The 24" anchor centers do not match the pedestal reconstruction detail that shows both 34" and 35.25" anchor centers both of which would require an even larger sole plate than listed or shown.  
Answer   Date: 9/14/2022 12:06:12 PM
Please see forthcoming revision 1 plan sheets 2, 7, and 11, which addresses all these questions.  
 
Subject: Arresting Cracks and Welding Type: Proposal
Question Date: 9/12/2022 10:47:57 AM
The proposal states arresting cracks and welding shall be included in the Structural Steel Rolled Beam item. The schedule of items includes an item for crack repair welding. Please confirm there is no expectation of crack repair to be incidental to the structural steel Rolled Beam item.  
Answer   Date: 9/14/2022 12:05:02 PM
Correct. Arresting of cracks will be paid for and performed as per ‘Crack Repair Welding’ pay item 68245.  
 
Subject: Reinforcing Steel for Expansion Joint Reconstruction & Backwall Reconstruction Type: Plan
Question Date: 9/12/2022 10:45:54 AM
There is no reinforcing steel detail shown for the Expansion Joint Reconstruction & Backwall Reconstruction items however note 4 on sheet 20 of 23 states new reinforcing steel to be lapped with existing longitudinal bars. Besides the replacement for bars with section loss, is there any intent to install new reinforcing bars in these areas?  
Answer   Date: 9/14/2022 12:04:38 PM
This is only intended if new bars (as directed by the Engineer) are required to replace the existing bars with a section loss as per Note 9 on Sheet 20.  
 
Subject: Rem. Portion of Existing Str. No. 2901 Type: Bid Sheet
Question Date: 9/12/2022 10:44:45 AM
A Rem. Portion of Existing Str. No. 2901 item is shown on plan sheet 3 of 23 but is not listed on the schedule of items. Please confirm where demolition items will be paid.  
Answer   Date: 9/14/2022 12:04:00 PM
Pay item 'Remove Portion of Existing Str. No. 2901' is no longer being used for the project. Sheet 3 is revised accordingly to remove this pay item. Items 68112, 68192, 68339, 68570, 68573, 68579, 69815 demolition is being paid for based on the individual pay items per the specifications or special provisions provided in the contract documents.  
 

Displaying questions 1 - 10 (of 16)