Project Info
Order Number UPC State Project Number Last Date to Post Questions
H64 17633 BW00-047-103,C501 10/21/2022
Search Questions
Search
Question Type  
    Export Q&A    
Question List
Subject: Type: Proposal
Question Date: 9/20/2022 4:02:28 PM
Can any type of Maple tree be substituted for the 24 each Jamestown Maples shown on the plans and in the proposal. These are very difficult to find at this time?  
Answer   Date:
 
 
Subject: Sheet 7(3) - Detail A Type: Plan
Question Date: 9/16/2022 2:45:01 PM
Please review Sheet 7(3) - Detail A. It appears that the existing signal junction box will be in the new CG-12 ramp. There are no construction details on how to handle this issue.  
Answer   Date: 9/21/2022 12:22:07 PM
Addendum is forthcoming. The Junction Box would be a reset, resulting in 1 qty of removal and 1 qty of install new JB- S2. However, the sidewalk for Detail A Sheet 7(3) is being installed by the developer, so those quantities will be necessary for the developer contractor to install, and not under this contract.  
 
Subject: Pushbutton Pay Items Type: Bid Sheet
Question Date: 9/16/2022 2:26:40 PM
Please review Line numbers 0940 and 1000. I believe these are duplicate items and one of them should be removed.  
Answer   Date: 9/21/2022 12:22:51 PM
Remove line 940, maintain line 1000. Addendum forthcoming.  
 
Subject: Sheet 7(3) - Loop Detectors Type: Plan
Question Date: 9/16/2022 2:25:25 PM
Are the loop detectors on sheet 7(3) (Sta. 105+00) to be replaced? If so, quantities will need to be added to the Schedule of Items.  
Answer   Date:
 
 
Subject: 16" Waterline Restoration Type: Plan
Question Date: 9/15/2022 1:24:36 PM
The 16" proposed waterline appears to be in Rt 60 in part. After the asphalt patching of the pipe trench will there be a need to mill and overlay one or both lanes in this area and relinestripe? If so, will these items be paid for at Contract unit pricing or included as incidental to the waterline install? If incidental, can you provide the limits of the mill and overlay required?  
Answer   Date: 9/16/2022 8:54:53 AM
No, there will be no milling, nor overlaying, nor any restriping in this area.  
 
Subject: Waterline Type: Specifications
Question Date: 9/14/2022 5:45:16 PM
Ductile Iron suppliers have notified us the 16" DI pipe has a 15 month lead time from the date of order. Assuming a contract is awarded November 1, 2022 the Substantial Completion Date of November 17, 2023 will not be met. Will the Department provide an extension to the Substantial Completion Date and Final Completion Date due to the delay in delivery of the DI pipe, valves and fittings?  
Answer   Date: 9/21/2022 12:23:39 PM
Substantial Completion Date and Final Completion Date will be revised in the forthcoming addendum.  
 
Subject: Demo Existing Sidewalk Type: Bid Sheet
Question Date: 9/14/2022 5:26:12 PM
The plans call for demolition of the existing sidewalk. Special Provision "Remove Sidewalk and Incidental Concrete Items" states there will be a pay item for "Remove sidewalk and entrance". Will this pay item be added?  
Answer   Date: 9/16/2022 8:52:19 AM
Yes, 256 SY of “Remove sidewalk and entrance” will be added via forthcoming addendum along with a revised plan sheet for clarification.  
 
Subject: SWM Basin Type: Proposal
Question Date: 9/14/2022 3:33:58 PM
Is a concrete cradle required for any of the pipe running through the SWM basins?  
Answer   Date: 9/16/2022 10:47:30 AM
Yes, line number 1200 in the Schedule of Items to read 8.24 instead of 2.24 CY. See forthcoming revision.  
 
Subject: Bio Retention Bedding Type: Plan
Question Date: 9/14/2022 9:53:43 AM
Is the bedding stone for the bio retention pond to be paid for under 00507?  
Answer   Date: 9/14/2022 1:50:24 PM
Yes.  
 
Subject: SWM Facility Type: Plan
Question Date: 9/9/2022 2:14:16 PM
The grading diagram does not include any quantities for the SWM facility shown being constructed on plan sheet 3. Will you add this quantity to the grading diagram and regular excavation pay item?  
Answer   Date: 9/12/2022 11:42:02 AM
SWM Excavation quantity of 61 CY (Item Number 27545) is shown in the Drainage Summary in sheet 2B(1). This same quantity is also shown in the Schedule of Items in the Contract Document. However, the table in the Grading Diagram and Summary sheet (sheet 2F) is only missing this quantity. This plan sheet (sheet 2F) will be updated to clarify via revision.  
 
Question Date: 9/12/2022 11:04:23 AM
Please delete this question  
Answer   Date:
 
 

Displaying questions 1 - 10 (of 14)