Project Info
Order Number UPC State Project Number Last Date to Post Questions
H60 109953 U000-110-191, C501, B602 9/23/2022
Search Questions
Search
Question Type  
    The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered. Export Q&A    
Question List
Subject: Double Box Culvert Type: Other
Question Date: 9/23/2022 3:30:38 PM
Please provide additional information about the existing double box culvert, we need to know the length of that Culvert to determine access to it.  
Answer   Date: 9/26/2022 10:38:40 AM
There are no available information on the existing box culvert beyond what are shown in the plans.  
 
Subject: Cofferdam Type: Other
Question Date: 9/23/2022 3:28:09 PM
Please provide the precise location where the cofferdams will be built.  
Answer   Date:
 
 
Question Date: 9/23/2022 3:28:07 PM
Please provide the precise location where the cofferdams will be built.  
Answer   Date: 9/26/2022 10:36:36 AM
The cofferdams are depicted on the E&S plans and intended to be moved as necessary by the contractor to maintain flow and allow for construction.  
 
Question Date: 9/23/2022 3:28:05 PM
Please provide the precise location where the cofferdams will be built.  
Answer   Date:
 
 
Question Date: 9/23/2022 3:28:01 PM
Please provide the precise location where the cofferdams will be built.  
Answer   Date:
 
 
Question Date: 9/23/2022 3:27:58 PM
Please provide the precise location where the cofferdams will be built.  
Answer   Date:
 
 
Subject: Cofferdam Type: Plan
Question Date: 9/23/2022 3:27:54 PM
Please provide the precise location where the cofferdams will be built.  
Answer   Date:
 
 
Subject: Existing Overhead Utility Lines Type: Other
Question Date: 9/22/2022 4:05:34 PM
Will an outage of the existing overhead utility lines on the west side of site be allowed? And if so, whom would be responsible for the related costs?  
Answer   Date: 9/24/2022 11:15:37 AM
 
 
Question Date: 9/22/2022 4:05:31 PM
Will an outage of the existing overhead utility lines on the west side of site be allowed? And if so, whom would be responsible for the related costs?  
Answer   Date: 9/24/2022 11:16:59 AM
No, an outage will not be allowed or acceptable for the overhead lines. If damaged or changes needed the cost would be borne by the contractor.  
 
Subject: Structures Excavation and Select Backfill Abutment Zone Type: Plan
Question Date: 9/22/2022 4:03:18 PM
Please reference bid items 0510 STRUCTURE EXCAVATION and 0520 SELECT BACKFILL ABUTMENT ZONE. The estimated quantities table on sheet 2D(2) notes that items to be paid for on the basis of plan quantities. Do the limits of shown on plans such as sheet 2D(3) need to be followed? Will the full bid quantity be paid regardless of actual quantity of work performed in field?  
Answer   Date: 9/24/2022 11:15:06 AM
Yes.  
 
Subject: Tree Removal Type: Plan
Question Date: 9/22/2022 3:52:08 PM
Per plan sheet 03B there are tree removals called out. Please confirm how those will be paid.  
Answer   Date: 9/24/2022 11:13:31 AM
Tree removal will be paid through clearing and grubbing.  
 
Subject: Bike Path Type: Plan
Question Date: 9/22/2022 3:49:30 PM
There is an existing bike path that ties into the proposed sidewalk at the NE quadrant of the project limits. Please confirm that can be closed during construction.  
Answer   Date: 9/24/2022 11:14:28 AM
Yes this tie in can be closed during construction.  
 
Subject: DISM.& REM.EX. STR. STR. VDOT#8000 Type: Bid Sheet
Question Date: 9/19/2022 4:57:18 PM
What is included in Proposal Line Number 0590, DISM.& REM.EX. STR. STR. VDOT#8000? Answer to the Proposal Line Number 0620, Disposal of Material Disposal of Material (Type B) question sent before, seems the same item.  
Answer   Date: 9/20/2022 4:49:13 PM
Proposal Line Number 0590, DISM.& REM.EX. STR. STR. VDOT#8000 includes the complete dismantling and removal of the existing structure. Proposal Line Number 0620, DISPOSAL OF MATERIAL DISPOSAL OF MATERIAL (Type B) is for the proper disposal of the dismantled existing structure which is designated as Type B Structure.  
 
Subject: Wingwalls Type: Proposal
Question Date: 9/17/2022 11:47:26 AM
Please clarify whether the cost of concrete for Wingwalls should be included in Architectural Treatment item or it will be paid under substructure concrete A3.  
Answer   Date: 9/19/2022 3:51:54 PM
The cost of concrete for wingwalls included in Item: Concrete Class A3. Measurement and payment for Architectural Treatment item is described in the special provisions. The concrete noted in the special provision is for the mockup/sample panel.  
 
Subject: Architectural Treatment Type: Proposal
Question Date: 9/17/2022 11:43:39 AM
Special Provisions for Architectural Treatment states that payment for Architectural Treatment of terminal walls includes concrete in terminal walls. However, Sheet 2D(15) shows that the limit of payment for Texas Classic Railing includes the Terminal wall. Please clarify whether the cost of concrete terminal wall should be included in the Architectural Treatment Item or it will be paid as part of Texas Classic Railing.  
Answer   Date: 9/19/2022 3:51:11 PM
The cost of the concrete terminal wall shall be included in the Texas Classic Railing as shown and noted in the construction plans. Measurement and payment for Architectural Treatment item is described in the special provisions. The concrete noted in the special provision is for the mockup/sample panel.  
 