Subject: FDR Type: Other
Question Date: 7/21/2022 3:53:08 PM
Are there any existing utilities within 24" of finished asphalt grade?  
Answer   Date: 7/22/2022 12:33:27 PM
The Contractor must comply with the Miss Utility law and identify any conflicts. Utility markings must be maintained as required by law.  
 
Subject: FDR Type: Specifications
Question Date: 7/20/2022 2:18:08 PM
Can the asphalt be milled off first? Or do you have to pre-pulverize prior to removing excess?  
Answer   Date: 7/20/2022 3:39:11 PM
Asphalt may be milled off first. However, this will not change the scope of the bid item nor its method of payment.  
 
Question Date: 7/18/2022 2:48:18 PM
Per addendum 1 on 7/14/2022, the specs do no specify using a curing seal or sand (no. 10 aggregate). The street list in the project proposal says to use a liquid asphalt for curing of cement and sand (see page 287 Rt. 2214, for example). Is the contractor required to use a curing seal or aggregate on top of the stabilized course?  
Answer   Date: 7/18/2022 3:53:15 PM
Please use a seal of liquid asphalt to cure.  
 
Question Date: 7/18/2022 2:47:20 PM
Per addendum 1 on 7/14/2022, the specs specify using 5% cement by weight for bidding purposes, but the street list in the project proposal say use 9% (see page 287 Rt. 2214, for example). Please verify which should be used.  
Answer   Date:
 
 
Question Date: 7/18/2022 2:47:18 PM
Per addendum 1 on 7/14/2022, the specs specify using 5% cement by weight for bidding purposes, but the street list in the project proposal say use 9% (see page 287 Rt. 2214, for example). Please verify which should be used.  
Answer   Date: 7/18/2022 3:51:55 PM
Mix design by contractor is not required. Please use the 9% by weight cement as specified.  
 
Question Date: 7/18/2022 2:46:40 PM
Per page 287 in the project proposal (Rt. 2214) the notes read that a mix design is not required, and the cement content is 9% by weight. Per the FDR specs posted on 7/14/2022, it reads that a mix design is required by the contractor. Can you verify if a mix design provided, by the contractor, will be required for this job?  
Answer   Date: 7/18/2022 3:51:14 PM
Mix design by contractor is not required. Please use the 9% by weight cement as specified.  
 