Order Number UPC State Project Number Last Date to Post Questions
G59 111689 0711-053-181, B603 3/4/2022
Search Questions
Search
Question Type  
    The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered. Export Q&A    
Question List
Subject: Lane Closures Type: Plan
Question Date: 3/8/2022 4:11:04 PM
Specs show lane closure limitation for this project. Is this applicable to this project given the low traffic volume of this road?  
Answer   Date:
 
 
Subject: Night Work Type: Specifications
Question Date: 3/8/2022 12:24:23 PM
Is nightwork permitted for this project? The specs are not clear on if night work is allowed in this area and additional time will be required due to the limited road closure noted in the addendum.  
Answer   Date: 3/8/2022 4:29:30 PM
Night work will be permitted per Limitaion of Operation Special Provision if the Contractor obtains all the necessary permits. The Contractor will be responsible to obtain all necessary permits including but not limited to noise ordinance permit.  
 
Subject: Conflicting Information Type: Specifications
Question Date: 3/8/2022 12:20:49 PM
Conflicting information has been provided. The VDOT standard specifications defines substructure work. One of the answers states that "All substructure work and other work may be performed within the allowable lane closure hours detailed in the Special Provision for Section 108.02 – Limitation of Operation." How is all substructure work installed without the road closure?  
Answer   Date: 3/8/2022 4:28:40 PM
The contractor will be allowed to perform any work that can be done prior and after full road closure per lane closure stated in the Special Provision for limitation of operation.  
 
Subject: Addenda Updated Bid Item Discrepancy Type: Bid Sheet
Question Date: 3/2/2022 10:21:11 AM
The Snapshot provided in ASHTOWare shows the Item 630 Disposal of Material was deleted; however, the bid items provided in BidX show the Construction Trailer was deleted. Please update the snapshot provided by ASHTOWare program to show the correct items.  
Answer   Date: 3/2/2022 11:49:54 AM
The referenced problem appears correct in all systems. Please ensure the amendment file has been applied, in order to show the correct Snapshot in AASHTOWare.  
 
Subject: Allowable work Type: Plan
Question Date: 3/2/2022 9:51:17 AM
What kind of work we can do before complete road closure? Can we do clearing and grubbing with partial lane closure? setting pipe, cofferdam, etc. OR We will have to do all after complete road closure?  
Answer   Date: 3/3/2022 10:52:13 AM
All substructure work and other work may be performed within the allowable lane closure hours detailed in the Special Provision for Section 108.02 – Limitation of Operation.  
 
Subject: precast Type: Other
Question Date: 2/25/2022 4:05:26 PM
As a precast supplier, provided we have a contract/PO by the beginning of April 2022 and shop drawings are reviewed and returned in a timely manner, mid summer erection date are reasonable.  
Answer   Date: 2/28/2022 12:17:28 PM
Shop drawing review will be prioritized. The turnaround time will be as short as possible.  
 
Subject: Project Completion Type: Specifications
Question Date: 2/23/2022 9:45:29 AM
Due to COVID-19 and now with the bid date extended further out, Precasters are excluding liability for meeting certain deadlines for having all precast structures ready in order to meet the Completion date of September 02, 2022. Therefore, can the Department allow a minim of 60-day full road closure to allow for completion of the project?  
Answer   Date: 2/28/2022 12:17:05 PM
No. The bridge is to be replaced Accelerated Bridge Construction Method and is not expected to take more than 30 days. Road closure shall be planned around the time the precast elements are expected to be at the site.  
 
Subject: Modified Double Seal Type: Plan
Question Date: 2/23/2022 8:35:23 AM
There is a section noting the Modified Double Seal is to be installed on top of the Asphalt, but the plans do not show the limits. Are we to follow the asphalt limits on sheet 3?  
Answer   Date: 2/28/2022 12:16:32 PM
Yes, the limits of the Modified Double Seal shall match the limits of the Proposed Asphalt as shown on Sheet 3.  
 
Subject: Line Item 510 Type: Bid Sheet
Question Date: 2/23/2022 8:33:07 AM
#510: Architectural Treatment Railing: Per drawings on sheet 21 of 25, the terminal wall shall receive this treatment but the quantity does not appear to be included in the line item (Under stated quantity). Please confirm where we are to account for the terminal wall treatment.  
Answer   Date: 2/28/2022 12:16:00 PM
The quantity for parapets should be 31 SY, and the quantity for terminal walls should be 52 SY.  
 
Subject: Line Item 520 Type: Bid Sheet
Question Date: 2/23/2022 8:19:56 AM
Item #520: Railing SPSR 2 Rail. The bid items show a quantity of 144 LF, however, the bridge is only 42' long. Where is the additional LF to be installed?  
Answer   Date: 2/28/2022 12:15:15 PM
The railing quantity for the superstructure is 84 LF. Terminal walls are categorized as a substructure payment (see plan sheet 20 “Elevation”), and the quantity is 60 LF. The total is 144 LF.  
 