Subject: DBE Participation Type: Other
Question Date: 2/8/2022 11:28:18 AM
If there is no DBE Goal, should we be prepared to submit the GFE Evidence?  
Answer   Date: 2/8/2022 11:59:08 AM
With no DBE Goal, you do not need to be prepared to submit the GFE Evidence.  
 
Question Date: 1/28/2022 9:06:48 AM
Are there DBE requirements for this project? If so, what is the goal?  
Answer   Date: 1/28/2022 11:17:44 AM
There is no DBE goal on this project.  
 
Subject: Bid letting Type: Proposal
Question Date: 1/13/2022 10:38:32 AM
When is the actual bid letting for this project? On CABB it says 2/23/2022 but on the actual Bid Proposal it lists 2/2/2022.  
Answer   Date:
 
 