Subject: Type 3 Barricades Type: Proposal
Question Date: 6/16/2021 4:38:10 PM
Are Type 3 Barricades paid each day per the number of barricades?  
Answer   Date: 7/1/2021 2:04:58 PM
TYIII Barricades shall be paid for in accordance with section 512.04 of the 2020 Road and Bridge Specifications.  
 
Subject: Sealcoat Distributor Type: Specifications
Question Date: 6/10/2021 4:45:57 PM
The single axle restriction listed on Pg 147 essentially limits this work to small trailed mounted spray units. Page 139 states that the distributor shall be equipped with a monitoring system that ensures the even distribution of material and measures the application rate. As far as I can find, there are no single axle units in production capable of meeting these requirements. Would other methods of measuring material and application rates?  
Answer   1 previous answer(s) Date: 6/18/2021 2:51:39 PM
If the contractor elects to not use a metering device, two tests will be taken per shift in accordance with section 310 in the 2020 Road and Bridge Specifications.  
 