Subject: Demolition of Pavement (Flexible) Type: Bid Sheet
Question Date: 5/14/2021 11:04:59 AM
Will a pay item for pavement removal be added?  
Answer   Date: 5/14/2021 3:21:17 PM
A revision has been processed adding 975 SY of Item 24430 Demo of Pavement (Flexible)  
 
Subject: Cross Sections Type: Plan
Question Date: 5/14/2021 10:55:26 AM
Are cross sections available for Sta 101+75 to 103+50 for the widening of Rte. 522?  
Answer   Date:
 
 
Question Date: 5/14/2021 10:53:59 AM
Are cross sections available for Sta 220+00 to 224+00 for the widening for the temporary pavement?  
Answer   Date:
 
 
Subject: plan sheet 2 - Grading . Type: Plan
Question Date: 5/13/2021 3:39:14 PM
plan sheet 2 - Grading - G-6, borrow and embankment to be CBR 15 but the second paragraph states soils encountered on the project are expected to meet these requirements. are you saying that the soils on site are CBR 15? if not, I am not sure what you are saying  
Answer   Date: 5/14/2021 3:00:56 PM
Based on the geotechnical borings and testing, we believe that on-site soils in the areas tested will meet a minimum CBR of 15 and should be acceptable as fill material."  
 
Subject: Progress Schedule Update Bid Item Type: Proposal
Question Date: 5/11/2021 4:34:21 PM
Bid item #25567 Progress Schedule Update shows a quantity of 28 ea. The fixed completion date for this project is Sept. 23, 2022. Assuming a 60 day award, that would leave about 14 months of duration for this project. Why does bid item #25567 have twice that quantity?  
Answer   Date: 5/12/2021 12:21:36 PM
Quantity of bit item #25567 should be 14 months.  
 
Subject: Nationwide Permit Type: Permits
Question Date: 5/6/2021 1:42:28 PM
The nationwide permit expires on 3/18/22. There is a time of year restriction for instream work from 10/1 - 3/31. Can the temporary causeway and cofferdam be removed after the permit has expired? If not can the permit be extended by the department?  
Answer   1 previous answer(s) Date: 5/12/2021 12:52:07 PM
The March 18, 2022 expiration date mentioned in the blue card packet is the boilerplate comment for all Nationwides. However, the NW3 permit was accompanied by the reporting RP-11 permit which moved the expiration date to September 20, 2024 (this meets the "unless indicated otherwise in the conditions specific to this project" criterion, so the date 3 pages earlier controls). The earliest expiration date of a permit for this project is the VGP-1 permit on February 14, 2023. If during construction it is discovered that the project may overrun the schedule such that cofferdam / causeway removal would occur after 2/14/2023, then we can obtain a permit extension.  
 
Subject: Payment Type: Plan
Question Date: 5/4/2021 3:14:42 PM
Will existing slope in front of Abutment A, outside of 18 inches be paid for under structure excavation?  
Answer   Date: 5/12/2021 12:53:12 PM
Excavation of the existing slope in front of Abutment A outside of 18 inches shall be paid for under lump sum Grading (item 00125)  
 
Subject: Early Completion Date Type: Proposal
Question Date: 5/4/2021 10:19:04 AM
The special provision indicates an early completion date of May 23, 2021. This must be a typo since the project bids on the May 26, 2021. Please advise what the actual early completion date for the project is.  
Answer   Date: 5/14/2021 3:25:07 PM
The early completion incentive / disincentive special provision should match the project completion date of September 23, 2022.  
 
Subject: Temporary Traffic Control Type: Plan
Question Date: 5/3/2021 1:07:58 PM
The typical section on sheet 1K for the southbound crossover refers to stations 102-108. Sheet 1 L (1) show approximately Stations 202-208. Which is correct?  
Answer   Date: 5/5/2021 10:26:40 AM
Sheet 1L(1) is correct, and sheet 1K left typical section should refer to stations 202-208. A revision will be forthcoming.  
 
Subject: Clarification on Bid Date Type: Proposal
Question Date: 4/28/2021 5:09:22 PM
Please provide clarification on the bid date. The VDOT CABB shows 6/23/21 however the cover sheet shows 5/26/21. Thanks,  
Answer   Date: 5/4/2021 11:50:41 AM
CABB has been corrected.  
 

Displaying questions 1 - 9 (of 9)