Subject: Full Depth Mill and Overlay Type: Plan
Question Date: 5/12/2021 11:22:38 AM
Does the note on plan sheet 1J(13) apply to all Full Depth Mill and Overlay? If not please clarify the depth of milling required for Full Depth Mill and Overlay  
Answer   Date: 5/13/2021 8:27:16 AM
The Note on sheet 1J(13) applies to all Full Depth Mill and Overlay. Depth is to be 7" of BM-25.0D and 4" of IM-19.0D  
 
Subject: Traffic Shift I81 N Type: Plan
Question Date: 5/12/2021 11:17:51 AM
Will the 3' lane shift on I 81 N require any modifications to the Guardrail Terminal section at approximate STA 428+00 or to the ditch and/or slope between approximate STA 413+25 and STA 427+00? Will pay items be added for 4" temporary payment markings, rumble strips and eradication required for this shift?  
Answer   Date:
 
 
Subject: Full Depth mill and Overlay I81 N Type: Plan
Question Date: 5/12/2021 10:59:55 AM
Plan sheets 1J(13) - 1J(17) show a 4' wide full depth mill and overlay on the inside I81 northbound lane. Note on sheet 1J(13) indicates Full Depth Mill and Overlay is 7" of Bm-25.0D and 4" of Im-19.0D. The plans also indicate Sawcut is required. Please confirm the limits of excavation are 4' from the traffic side of the yellow line and a depth of 11" ( i.e..no additional excavation is required for stone is required. Please confirm that Sawcut will be paid even though it is performed performed concurrently with the milling and by the milling machine,  
Answer   Date: 5/13/2021 8:27:50 AM
Limits of Excavation are 4' from the yellow line with a depth of 11 inches. Sawcut will not be paid in areas of full depth mill and overlay.  
 
Subject: Slope failure Type: Plan
Question Date: 5/10/2021 10:33:36 AM
Is the slope failure above STR 3-5 to be included in repair cost to replace the wing wall?  
Answer   Date: 5/13/2021 8:26:27 AM
Reestablishment of the slope above STR 3-5 should be included in the repair cost to replace the wing wall. Rolled erosion control slope stabilization matting is provided in the schedule of items.  
 

Displaying questions 1 - 4 (of 4)