Subject: Completion Date Type: Proposal
Question Date: 5/14/2021 10:08:30 AM
The Completion Date on the Notice of Advertisement and CABB show April 13, 2022. The C-7 shows June 23, 2022. Which date is correct?  
Answer   Date: 5/14/2021 10:19:15 AM
April 13, 2022 is the correct completion date. The C-7 will be updated by addendum to reference April 13, 2022.  
 