Subject: 0470 Conc. Found. STP-2 Ty D Type: Bid Sheet
Question Date: 5/13/2021 1:22:17 PM
Please clarify that this foundation will be used for the 2" post. The STP-1 2" usually requires a STP-1 Ty A, B, C, D, or E. Please clarify the foundation and post required for this project.  
Answer   Date:
 
 
Subject: 8 Conductor Cable Type: Specifications
Question Date: 5/12/2021 4:01:11 PM
According to the specification 8 cond cable (furnish & install) is included in the modify items. Is this different than the line item 0660 55080for 8 cond cable. Please clarify.  
Answer   Date:
 
 
Subject: Coaxial Cable Type: Plan
Question Date: 5/12/2021 3:56:35 PM
Note 10 on sheet 5(2) states that the existing coaxial cable is to be removed and not replaced. According to the plans there is new coaxial cable shown in the conduit runs. If coaxial cable is needed a line item will need to be added.  
Answer   Date: 5/13/2021 1:54:05 PM
Pay Item 51508 (coaxial cable) on Sheet 5(4) is to be used for the video detection cameras for the traffic signal modifications on sheet 5(1) and sheet 5(3).  
 
Subject: Existing Junction Boxes Type: Plan
Question Date: 5/12/2021 3:54:41 PM
Will the contractor need to remove any of the existing junction boxes? If so, will you be adding a line item?  
Answer   Date:
 
 
Subject: Sign Panel Type: Bid Sheet
Question Date: 5/12/2021 2:22:37 PM
Will you be adding a line item for the sign panel per sf?  
Answer   Date:
 
 
Subject: Line Item 0590 Install Conduits on Bridge Type: Plan
Question Date: 5/12/2021 9:57:02 AM
Would VDOT entertain deleting this item and installing conduit by boring? Several things to consider: cost savings for traffic control, less interruption for traffic, cost savings for the Engineer, and this will not have to be redone when it's time for the bridge to be replaced.  
Answer   Date: 5/13/2021 8:28:42 AM
No. The conduit shall be installed on the bridge as specified.  
 
Subject: Bid Item Schedule vs. Summary Sheets Type: Bid Sheet
Question Date: 5/3/2021 2:33:45 PM
Why is there such a discrepancy between the quantity of some of the items in the Bid Item Schedule and the amounts shown on the Summary Sheet or able to be taken off the plan sheets? Bid Item 400 EC-2 Type 3 - Bid Item Schedule is 1,200 SY while the ESC Summary on 2B shows none. Bid Item 410 EC-2 Type 3 - Bid Item Schedule is 6,000 SY while Sheet 2B is 331 SY. Bid Item 420 - A previous question has already listed this discrepancy. Bid Item 430 Siltation Control Excavation - Bid Item Schedule is 374 CY while Sheet 2B is 128 CY. Bid Item 440 Silt Fence Type A - Bid Item Schedule is 2,200 LF while Sheet 2B is 725 LF.  
Answer   Date: 5/13/2021 8:44:31 AM
Bid Item 400 EC-2 Type 3 - Bid Item Schedule is 1,200 SY while the ESC Summary on 2B shows none. EC-2 Type 3 matting is not used Bid Item 410 EC-2 Type 3 - Bid Item Schedule is 6,000 SY while Sheet 2B is 331 SY. 331 SY is correct Bid Item 420 - A previous question has already listed this discrepancy. Bid Item 430 Siltation Control Excavation - Bid Item Schedule is 374 CY while Sheet 2B is 128 CY. 128 CY is correct Bid Item 440 Silt Fence Type A - Bid Item Schedule is 2,200 LF while Sheet 2B is 725 LF. 725 is correct  
 
Question Date: 5/14/2021 10:28:39 AM
Will a revised Schedule of Items be issued for this project?  
Answer   Date:
 
 
Question Date: 5/13/2021 9:58:27 AM
Bid item 0660 8 cond cable has 2,505 in the bid schedule and 4,020 on the plan sheets, 0680 JB-S4 has 10 in the bid schedule and 9 on the plan sheets, 0690 2" bored has 630 in the bid schedule and 705 on the bid sheet, 0710 2" PVC has 2,940 on the bid schedule and 3,590 on the bid sheet, 0730 has 1,330 in the bid schedule and 1,480 on the plan sheets.  
Answer   Date:
 
 
Subject: Water & Sewer Casings Type: Plan
Question Date: 5/3/2021 1:55:07 PM
Sheet 3 shows a note, "Extend 24" water and sewer casings to edge of fill or ditch per A.C.S.A Std. Detail G6." Is this part of our scope?  
Answer   Date: 5/13/2021 8:48:29 AM
Yes. This work will be performed as a part of the contract  
 
Question Date: 5/14/2021 10:28:06 AM
Where will this item be paid?  
Answer   Date:
 
 
Subject: Cross sections Type: Plan
Question Date: 5/3/2021 10:47:21 AM
There are several discrepancies in the cross sections. The 5' paved shoulder in shown 1 1/2" higher than the roadway asphalt. The typical section does not match the cross sections for make up of base stone and asphalt. These items are needed for lump sum earthwork quantities.  
Answer   Date:
 
 
Subject: Demolition of Existing Guardrail Type: Bid Sheet
Question Date: 4/29/2021 11:41:56 AM
Will the demolition of the existing guardrail be paid under Bid Item 0030 Grading or will a bid item for 24600 Remove Existing Guardrail be added to the Schedule of Items?  