Subject: Removal of Excess Material Type: Proposal
Question Date: 4/6/2021 4:19:34 PM
There is only a bid item for edge milling. If the current roads elevations need to stay the same, then there will need to be at least 2.5 inches removed from the entire cross section. This is due to the additional fluff from the FDR and the new 1.5" of asphalt pavement that will be placed. Will you consider adding a pay item for the additional removal needed to meet the final elevations?  