Project Info
Order Number State Project Number Last Date to Post Questions
A11 0017-034-911, B646, C501 8/21/2026
Question
Question Date: 7/13/2026
No addendum was received notifying contractors of the R1 and R2 plan sheet revisions posted to the ProjectWise site. Are R1 and R2 Plan sheet revisions part of the contract documents? If so, please issue another addendum formally adding them to the contract and also allow additional time to the bid for contractors to the review the 53 additional plan sheets and prepare a responsible bid.
Answer History
Previous Answers PostDate
This project has been delayed and we will release official notices of all plan changes. 7/17/2026
An addendum is forthcoming. 7/17/2026