Please be advised that there are four (4) amendments in BidX: C0000119384C01.ebsx; C000019384C01.001x; C000019384C01.002x; C000019384C01.003x. Also, please note that there is regular excavation shown in the temporary traffic control summary on sheet 2D(1). Line 0360 Regular Excavation in the SOI is 61,526 CY. The Temporary Traffic Control Summary on Sheet 2D(1) includes 770 CY of Regular Excavation. The Grading Summary on Sheet 2K(2)_r5 includes 60,756 CY of Regular Excavation. The total of 2D(1) and 2K(2)_r5 is 61,526 CY.
|