Question
Question Date: 1/17/2023
Note 22 on page 127 of the proposal says that "no jacking or repairs shall be performed within a span lane that is under traffic unless approved by the Engineer." Will the Engineer approve performing jacking operations or repairs under traffic if an adequate jacking and blocking plan is presented to the Department and approved? The traffic management plan indicates regular lane closures can only be in place from 8pm to 6am. The work shown in the plans cannot be performed in one 10-hour shift.
Answer History
Previous Answers PostDate
Yes, but traffic will not be allowed in the span lane until the beams are blocked or the jacks are locked. The allowable work hours provided must be adhered to when impacting traffic. The Department would anticipate work being done in phases with the bridge jacked and blocked. 1/19/2023
Yes, but traffic will not be allowed in the span lane until the beams are blocked or the jacks are locked. 1/19/2023