    The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered. Export Q&A    
Question List
Subject: Flow Rates Type: Plan
Question Date: 10/17/2019 3:59:10 PM
In order to meet the requirement of Note 5 on Sheet 3B, please provide flow rates for both Sallee Creek and the "creek" that enters Sallee Creek downstream of the existing structure on the south side of the roadway.  
Answer   Date: 10/21/2019 3:56:19 PM
Normal stream flow calculations are not available.  
 
Subject: ROAD CLOSURE Type: Permits
Question Date: 10/16/2019 1:52:56 PM
Will the road (Old Buckingham) be fully closed for the duration of the Project?  
Answer   1 previous answer(s) Date: 10/22/2019 8:55:04 AM
Route 13, Old Buckingham Road shall only be closed and the detour implemented after the Contractual NTP of June 15, 2020. The detour must be removed on or before the final completion date of August 31, 2020.  
 
Subject: Existing Utility Type: Other
Question Date: 10/14/2019 9:18:43 AM
Will the existing utility that is attached to the bridge be relocated prior to NTP?  
Answer   Date: 10/16/2019 1:58:41 PM
The bridge attachment (Verizon) is abandoned. New cable was placed off the bridge connecting new pedestals and bored under the creek. The "As-Builts" are complete for each relocation and are available to the winning construction bidder.  
 
Subject: Existing Structure Type: Plan
Question Date: 10/14/2019 9:17:49 AM
Are as-built plans available for the existing structure?  
Answer   Date: 10/16/2019 1:36:35 PM
As built plans are available in ProjectWise.  
 