Advertisements
Division Home
Bid Results
Bid Tabs
Ad Report
VDOT Forms
Login Or Create Account
Project Info
Order Number
UPC
State Project Number
Last Date to Post Questions
A99 N/B
81548
(NFO)0606-010-196, B635
5/17/2019
Search Questions
Search
Question Type
All
Plan
Proposal
Bid Sheet
Permits
Specifications
Other
Question Type must be selected.
The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered.
Export Q&A
Question List
Subject:
Completion Date
Type:
Proposal
Question
Date:
5/3/2019 8:34:27 AM
This completion date seems aggressive for a two phase deck with cast in place railing. Would the department consider a time extension?
Answer
Date:
5/7/2019 11:10:25 AM
We have reviewed the fixed completion date and feel there is adequate time to complete the project within the time frame.
Question
Date:
5/17/2019 8:25:03 AM
After viewing the contract plans, and the time allotted to complete, there is no way this project can be completed by the fixed date of November 18, 2019. With a poured in place deck, one half at a time, installing false work and cure time for deck and railing, this project will most likely run into the spring of 2020. the department should take a closer look at the work involved and with unstable weather, the fixed date should be considered prior to letting this project out for bids.
Answer
Date:
5/21/2019 3:14:04 PM
We have reviewed the fixed completion date and feel there is adequate time to complete the project within the time frame.
Question
Date:
5/9/2019 6:54:26 AM
With an estimated start date of 7/22/2019, the project time is approximately 120 days. The project is two phases with a cast in place deck and railing. The department's specifications require concrete to have 28 day strength on the deck and railing before traffic is permitted on the structure. Depending on strength gains of the concrete it is possible that 112 days could be required for the deck and railing to reach design strengths, making the project impossible to complete by November 18, 2019. These time frames do not include cure time for the substructure modifications. With this in mind, would the department consider adjusting the fixed completion date.
Answer
Date:
5/21/2019 3:14:16 PM
We have reviewed the fixed completion date and feel there is adequate time to complete the project within the time frame.
Displaying questions 1 - 1 (of 1)
Page:
1
First
Previous
Next
Last
Construction Advertisement Bulletin Board (CABB)
Update Profile
CABB v2.0
© 2008 Virginia Department of Transportation
5/8/2024 6:00:34 PM
2008