Project Info
Order Number
UPC
State Project Number
Last Date to Post Questions
A73
114328
(NFO)0664-965-358, N501, B602
5/17/2019
Search Questions
Search
Question Type
All
Plan
Proposal
Bid Sheet
Permits
Specifications
Other
Question Type must be selected.
The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered.
Export Q&A
Question List
Subject:
Plan Holders List
Type:
Plan
Question
Date:
5/20/2019 1:59:30 PM
I do not see the Plan Holders list for A73. Will it be uploaded soon?
Answer
Date:
5/20/2019 3:47:28 PM
The plan holders list is now showing in ProjectWise.
Subject:
JRB Lane Closure
Type:
Plan
Question
Date:
5/17/2019 12:49:06 PM
Can Lane Closures be set on JRB, or do they need to be set prior to the bridge?
Answer
Date:
Subject:
JRB Page 124
Type:
Plan
Question
Date:
5/17/2019 12:47:35 PM
JRB Task Order 003 does not contain marine access. Is this contractor to assume this is all to be done under lane closures and snoopers? Will VDOT entertain a per day snooper line item?
Answer
Date:
Subject:
Expansion Joint Recon Payment
Type:
Bid Sheet
Question
Date:
5/17/2019 12:13:57 PM
(Page 117) Is the Expansion Joint Recon being paid per side or both sides of the joint?
Answer
Date:
Subject:
Page 128 Joint Forming Details-Joint RECON
Type:
Plan
Question
Date:
5/17/2019 12:10:51 PM
Page 128 'This detail shows an approved method of forming at joints where type B patching extends to the end of the deck slab and the joint sealer is to be left in place." "Joint sealer to be left in place" Please explain how this can be done. How is the contractor to remove the epoxy adhesive from the existing joint and separate the concrete from the seal?
Answer
Date:
Question
Date:
5/17/2019 12:31:14 PM
Page 128- Will the contractor have to perform a leak test on the approved adhesive sealer? If yes, and the leak test fails, what are the next steps for the contractor?
Answer
Date:
Question
Date:
5/17/2019 12:27:24 PM
Page 128- "After removal of aluminum bulkhead (road sign), an approved adhesive sealer shall be applied to the joint sealer to provide watertight seal." How will this adhesive sealer be paid?
Answer
Date:
Subject:
Contract Start Date VS Contract End Date
Type:
Plan
Question
Date:
5/17/2019 11:57:01 AM
If a large marine task was to be issued, it is safe to assume a start date of September 3, 2019 in the water. Due to weather/ temperature restrictions, marine work would be shutdown the end of November. A re-mobilization April 1, 2020, then end date of Term 1 May 12, 2020. This is a total of 4 months 12 days marine work, minus weather days/holidays. Would Vdot entertain a later end date for Term 1?
Answer
Date:
Question
Date:
5/17/2019 11:56:59 AM
If a large marine task was to be issued, it is safe to assume a start date of September 3, 2019 in the water. Due to weather/ temperature restrictions, marine work would be shutdown the end of November. A re-mobilization April 1, 2020, then end date of Term 1 May 12, 2020. This is a total of 4 months 12 days marine work, minus weather days/holidays. Would Vdot entertain a later end date for Term 1?
Answer
Date:
Subject:
Lane Closure Hours / Availability
Type:
Proposal
Question
Date:
5/16/2019 12:49:42 PM
Will the contractor be guaranteed 5 lane closures per week, 8 hours per shift minimum, to work?
Answer
Date:
5/20/2019 1:19:59 PM
They are not guaranteed 5 lane closures per week. The Contractor shall coordinate with other operations.
Subject:
Beam End Repair
Type:
Bid Sheet
Question
Date:
5/16/2019 12:47:28 PM
Page 117 "No Beam End Repair shall be performed in a span lane that is under traffic." Please update the contractors on lane closure hours for the respective structures.
Answer
Date:
Subject:
Shotcrete Nozzlemen
Type:
Proposal
Question
Date:
5/16/2019 12:38:53 PM
What does VDOT require for a Nozzlemen to be certified for this project? If mock ups are desired, is that an incidental item to the contract?
Answer
Date:
5/20/2019 1:16:17 PM
Nozzlemen with at least 100 hours of recent similar shotcrete application experience and supervisors with at least 3 years of recent similar shotcreting experience who can provide references showing satisfactory performance on at least three similar jobs may be approved as being qualified without gunning prequalifying panels. Mock ups will be incidental to the contract.
Subject:
Marine Winter Shutdown / Spring Remob
Type:
Proposal
Question
Date:
5/16/2019 12:37:10 PM
December-March are unworkable months due to weather conditions/ temperatures. Would VDOT entertain a winter demobilization / spring remobilization line item? Page 103, Renewable On Call Contracts General Provisions; If this contract is renewed for the total term of 3 years, having one mobilization to blanket all the mobilizations and remobilizations would be difficult to calculate.
Answer
Date:
5/20/2019 1:14:32 PM
Scope of work and work quantities have been already distributed per term year at each structure per task order. Each task order is anticipated to be completed in each term year. A new task order (at same location) will be issued the following term year(s).
Displaying questions 1 - 10 (of 16)
Page:
1