Subject: Plan Holders List Type: Plan
Question Date: 5/20/2019 1:59:30 PM
I do not see the Plan Holders list for A73. Will it be uploaded soon?  
Answer   Date: 5/20/2019 3:47:28 PM
The plan holders list is now showing in ProjectWise.  
 
Subject: JRB Lane Closure Type: Plan
Question Date: 5/17/2019 12:49:06 PM
Can Lane Closures be set on JRB, or do they need to be set prior to the bridge?  
Answer   Date:
 
 
Subject: JRB Page 124 Type: Plan
Question Date: 5/17/2019 12:47:35 PM
JRB Task Order 003 does not contain marine access. Is this contractor to assume this is all to be done under lane closures and snoopers? Will VDOT entertain a per day snooper line item?  
Answer   Date:
 
 
Subject: Expansion Joint Recon Payment Type: Bid Sheet
Question Date: 5/17/2019 12:13:57 PM
(Page 117) Is the Expansion Joint Recon being paid per side or both sides of the joint?  
Answer   Date:
 
 
Subject: Page 128 Joint Forming Details-Joint RECON Type: Plan
Question Date: 5/17/2019 12:10:51 PM
Page 128 'This detail shows an approved method of forming at joints where type B patching extends to the end of the deck slab and the joint sealer is to be left in place." "Joint sealer to be left in place" Please explain how this can be done. How is the contractor to remove the epoxy adhesive from the existing joint and separate the concrete from the seal?  
Answer   Date:
 
 
Question Date: 5/17/2019 12:31:14 PM
Page 128- Will the contractor have to perform a leak test on the approved adhesive sealer? If yes, and the leak test fails, what are the next steps for the contractor?  
Answer   Date:
 
 
Question Date: 5/17/2019 12:27:24 PM
Page 128- "After removal of aluminum bulkhead (road sign), an approved adhesive sealer shall be applied to the joint sealer to provide watertight seal." How will this adhesive sealer be paid?  
Answer   Date:
 
 
Subject: Contract Start Date VS Contract End Date Type: Plan
Question Date: 5/17/2019 11:57:01 AM
If a large marine task was to be issued, it is safe to assume a start date of September 3, 2019 in the water. Due to weather/ temperature restrictions, marine work would be shutdown the end of November. A re-mobilization April 1, 2020, then end date of Term 1 May 12, 2020. This is a total of 4 months 12 days marine work, minus weather days/holidays. Would Vdot entertain a later end date for Term 1?  
Answer   Date:
 
 
Question Date: 5/17/2019 11:56:59 AM
If a large marine task was to be issued, it is safe to assume a start date of September 3, 2019 in the water. Due to weather/ temperature restrictions, marine work would be shutdown the end of November. A re-mobilization April 1, 2020, then end date of Term 1 May 12, 2020. This is a total of 4 months 12 days marine work, minus weather days/holidays. Would Vdot entertain a later end date for Term 1?  
Answer   Date:
 
 
Subject: Lane Closure Hours / Availability Type: Proposal
Question Date: 5/16/2019 12:49:42 PM
Will the contractor be guaranteed 5 lane closures per week, 8 hours per shift minimum, to work?  
Answer   Date: 5/20/2019 1:19:59 PM
They are not guaranteed 5 lane closures per week. The Contractor shall coordinate with other operations.  
 
Subject: Beam End Repair Type: Bid Sheet
Question Date: 5/16/2019 12:47:28 PM
Page 117 "No Beam End Repair shall be performed in a span lane that is under traffic." Please update the contractors on lane closure hours for the respective structures.  
Answer   Date:
 
 
Subject: Shotcrete Nozzlemen Type: Proposal
Question Date: 5/16/2019 12:38:53 PM
What does VDOT require for a Nozzlemen to be certified for this project? If mock ups are desired, is that an incidental item to the contract?  
Answer   Date: 5/20/2019 1:16:17 PM
Nozzlemen with at least 100 hours of recent similar shotcrete application experience and supervisors with at least 3 years of recent similar shotcreting experience who can provide references showing satisfactory performance on at least three similar jobs may be approved as being qualified without gunning prequalifying panels. Mock ups will be incidental to the contract.  
 
Subject: Marine Winter Shutdown / Spring Remob Type: Proposal
Question Date: 5/16/2019 12:37:10 PM
December-March are unworkable months due to weather conditions/ temperatures. Would VDOT entertain a winter demobilization / spring remobilization line item? Page 103, Renewable On Call Contracts General Provisions; If this contract is renewed for the total term of 3 years, having one mobilization to blanket all the mobilizations and remobilizations would be difficult to calculate.  
Answer   Date: 5/20/2019 1:14:32 PM
Scope of work and work quantities have been already distributed per term year at each structure per task order. Each task order is anticipated to be completed in each term year. A new task order (at same location) will be issued the following term year(s).  
 

Displaying questions 1 - 10 (of 16)