Project Info
Order Number
UPC
State Project Number
Last Date to Post Questions
N74
104189
(NFO) 0224-084-S12, C501
7/20/2018
Search Questions
Search
Question Type
All
Plan
Proposal
Bid Sheet
Permits
Specifications
Other
Question Type must be selected.
The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered.
Export Q&A
Question List
Subject:
Quality Control
Type:
Other
Question
Date:
7/18/2018 10:19:18 AM
Will the Contractor be required to furnish his own QC testing, or will VDOT perform all testing required on the site?
Answer
Date:
7/23/2018 3:57:28 PM
The contractor will need to perform their own QC testing as the Department will only perform testing as required within the VDOT guidance documents. The Contractor shall perform any QC control measures for themselves unless here within specified.
Subject:
Revised Plan sheets
Type:
Plan
Question
Date:
7/17/2018 11:37:03 AM
Addendum noted that plan sheets 2D(1) and 3 revisions would be available on Project Wise Site. Where are those sheets located?
Answer
Date:
7/23/2018 1:33:10 PM
Plan sheets 2D(1) and 3 can be found in ProjectWise via following folder path: Plan File Room > Road Plans > Bristol > 0224-084-s12,c501.
Subject:
Overhead Electric Lines
Type:
Plan
Question
Date:
7/17/2018 11:34:22 AM
Will the Overhead Electrical lines to the houses to be demolished taken down by the power company, or will the Contractor have to take them down?
Answer
Date:
7/23/2018 1:36:50 PM
The Overhead Electrical lines to the houses to be demolished will be taken down by the power company.
Subject:
Mitigation Site Survey
Type:
Specifications
Question
Date:
7/17/2018 11:30:37 AM
Special Provision for Compensatory Mitigation Site Survey Data was added per addendum. Where on the plans is this environmental sensitive site located and will there be a bid item added for this work as per the measurement and payment portion of provision?
Answer
Date:
7/23/2018 2:58:11 PM
This provision was mistakenly included with the revision. It will be removed via revision prior to execution as there are no compensatory mitigation associated with this project.
Subject:
Asbestos Survey
Type:
Proposal
Question
Date:
7/16/2018 12:14:33 PM
No asbestos survey was found in the bid documents. Please provide documentation including an asbestos survey or other documentation supporting the existence and quantity of asbestos as delineated on the bid schedule.
Answer
Date:
Subject:
Geotechnical Information
Type:
Other
Question
Date:
7/10/2018 10:11:11 AM
Were there any borings taken in the cut for this project, or a Geotechnical Report done?
Answer
Date:
7/17/2018 5:12:27 PM
Geotechnical Report has been uploaded to Falcon.
Subject:
Plans Not Available
Type:
Plan
Question
Date:
6/21/2018 10:05:31 AM
Answer
Date:
Displaying questions 1 - 7 (of 7)
Page:
1
First
Previous
Next
Last