Project Info
Order Number UPC State Project Number Last Date to Post Questions
948 112175 (NFO)PM9I-029-F18, N501 3/23/2018
Search Questions
Search
Question Type  
    The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered. Export Q&A    
Question List
Subject: Asphalt Spec Type: Specifications
Question Date: 3/19/2018 11:38:37 AM
On page 171, the specification for 25mm +0.4 HMHB in table 3 it talks about 64H-22 & 64S-22 depending on the amount of RAP used in the mix . On page 189 in the detail for the patching, 70-22 is shown on the detail. On page 192 the notes call out to used 76-22 for the 25mm +0.4 HMHB. We need a clarification on which AC will be required for the 25mm +0.4 HMHB for this project. Is it the 76-22 or is it 70-22?  
Answer   Date: 3/23/2018 11:01:04 AM
An addendum has been issued to change the contract details and notes.  
 
Subject: Specification Questioons Type: Specifications
Question Date: 2/26/2018 9:11:17 AM
Will all 9 questions and answers from the original bid of Order Number 948 on January 24 apply to this bid as well?  
Answer   Date:
 
 

Displaying questions 1 - 2 (of 2)